Fort Belvoir Historic Rehabilitation

admin November 8, 2020 Leave a reply

US Army Design Build Exterior Rehabilitation of Historic Buildings at Fort Belvoir in Fort Belvoir, Virginia

General Synopsis

This initial contract was for the design and historical rehabilitation of five (5) separate historic buildings located at Ft. Belvoir, VA. Buildings 212, 213, 219, 240 and 256 were rehabilitated in a manner consistent with the Secretary of the Interior’s Standards and Guidelines for Rehabilitation. Work on this historic rehabilitation project included the replacement of storm windows, painting windows, tucks pointing, masonry repairs, brick replacement and power washing. The contract cost increase was due to the client adding two (2) additional buildings to the scope. Meltech received an outstanding rating on this project on this high-profile command interest project. Meltech self-performed approximately 30% of the work on this project including project management, supervision, QAQC, Safety, and general conditions, window installation, painting and power washing. The client was extremely satisfied with Meltech’s work and added 2 additional buildings to the original scope of work.

Meltech provided 35%, 65%, and 95% design documents for the completion of all tasks.

Challenges that were successfully overcome included the fact that lead-based paint was presumed to be present on all buildings, so all loose and flaking paint had to be removed prior to any work being undertaken. Paint chips resulting from the removal work were treated as hazardous material and were disposed of by the client.

Further Details

Building 212 had a general scope of rehabilitation that included:

  • cleaning of the building exterior,
  • repair of damaged and failing masonry (including improvements to past improper repairs)
  • painting and repairs to wood elements such as windows and cornice, dormers and trim
  • foundation and concrete wall repairs including repair of all general cracking with injection grout
  • foundation preparation, priming and painting of the concrete foundation wall and porch to match surrounding structures,
  • painting of metal rails
  • Repairs to brick walls including
    1. Removal of heavy bituminous staining and paint splatter from brick surfaces
    2. Removal and repair of all extraneous penetrations which included pipes, nails, attachments and anchors
    3. Provision of copper chimney cap to cover and seal uncapped chimney
    4. Repointing and stabilization of brick chimney
    5. Replacing poor and failing masonry repairs with brick and mortar
  • Repairs to windows and doors including reparation, priming and painting of all exterior wood doors, trim and associated transom

Building 213 was in a similar state and had similar needs to building 212 above with the addition of:

  • Repairs to a slate roof including:
    1. Repair/replace/rehanging of all copper gutters and downspouts and installation of leaf guards
    2. Repair of damaged downspouts and replacement with in-kind materials
    3. Reconnection of all downspout as to subterranean drainage system
    4. Installation of missing cast iron downspout boots
  • Porch, step and ramp repairs including caulking the junctures between steps, ramps, landings, and building foundations and adjacent sidewalks

Building 219 had originally been a theater and gymnasium and now featured administrative space in lieu of the gymnasium. The building had a complex footprint and employed two different roof types – a one story brick hyphen connecting to two two-story brick wings, with the hyphen terminating in a side gable roof with gable dormers. The repairs to this building were of similar type to buildings 212 and 213 above but required extra awareness of the roof geometry. The suite of repairs for this building included:

  • Cleaning (10,000 sf)
  • Foundation repairs
  • Wood cornice, eaves, siding, parapet, column, pediment, pilaster and trim repairs
  • Brick wall repairs including replacement of a number of damaged bricks, removal of all abandoned electrical conduit/pipe , repair of spalling masonry at door surround keystone
  • Concrete wall repairs
  • Window and wood repairs, similar to two buildings above, but including in addition replacement of failed glazing compound, repair and replacement of rotted wood as needed, provision of exterior storm windows with low-emission glass coatings and screens
  • Porch, step and ramp repairs
  • Site work
  • Roof repairs
  • Exterior lighting including repair and rewiring of historic lights and carriage lamps and demolition of existing security lights and conduit and replacement with new fixtures with interior wiring incorporating full cut-off and LED wall packs

Building 240 had a general scope of repair similar to the above buildings but required that stucco elements of design be addressed and work on a rear loading dock and main entrance façade be included. The suite of repairs for this building included:

  • Cleaning
  • Stucco, cornice, eaves, siding, parapet, column, pediment, pilaster and trim repairs, including repair, treatment and painting of a stucco tower
  • Brick wall repairs including full suite as in building 219 above plus verification and confirmation of pointing on an existing stone chimney cap
  • Concrete and precast repairs including suite of repairs as in building 219 plus repairing a concrete failure on a rear loading dock, repairing concrete cracking on a rear loading dock, and installing rubber bumpers on a rear-loading dock.
  • Window and wood repairs
  • Porch, step and ramp repairs
  • Site work
  • Roof repairs

Building 256 had a general scope of rehabilitation that included:

  • Cleaning
  • Foundation repairs
  • Wood cornice, eaves, siding, and trim repairs
  • Brick wall repairs similar to building 240 above also but including cleaning heavy dirt/organic/chemical staining
  • Window and wood repairs, similar to buildings 204 and 219 above, but including in addition
    1. Replacing an existing steel door with a custom made replacement unit, frame and locking mechanism manufactured to fit in the existing opening and including all flashings, door sweeps, threshold and weather stripping,
    2. Removing an existing double doors and frame and replacing with new steel doors, frame and locking mechanism, with all similar in detail to the historic entrance doors
    3. Replacing a rotted/ rusting exterior door and frame with a replacement similar in historic detail with a four-paned window,
    4. Restoring a fanlight window above a ceremonial entrance
    5. Removal of a set historically inaccurate replacement windows
    6. Replacement of a set of ordinary windows with historically sensitive steel hopper industrial windows,
  • Site work
  • Gable roof addition repairs
  • Exterior lighting

WSSC Data Center

admin November 8, 2020 Leave a reply

Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades

Meltech was awarded this task order under our WSSC RGH Data Center Upgrades SATOC. This project was for the Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades in Laurel, Maryland. The work for this data center renovation included the following: 

  • Replacement of computer room air conditioning units in Main Computer Room and associated dry coolers and pump packages. Removal of air conditioning units in third floor PBX room and mechanical room adjacent to lake level UPS room. Replacement of ventilation fan in penthouse mechanical room.
  • New air conditioning units in PBX room and associated dry coolers and pump packages. New air conditioning units in Lake Level mechanical room to support both UPS rooms and adjacent spaces.
  • New static uninterruptible power supply, automatic transfer switch (ATS), power distribution units and panelboards to support Main Computer Room.
  • Replacement of lighting fixtures in room 3025, circuit breakers in panelboards with associated conduits, cables and other appurtenances shown on the drawings.
  • Replacement of floor tiles in the Main Computer Room and room 3025.
  • Replacement of wet pipe sprinkler system with pre-action type. Replacement of Halon fire suppression system with FM-200 system.

Fort Belvoir Design Build Community Care Unit

admin November 8, 2020 Leave a reply

US Army Design Build Renovations at Fort Belvoir Community Care Unit Building 802 at Fort Belvoir, Virginia

Meltech was awarded this project to provide all materials, labor, equipment, transportation, and services to complete the design and build and renovation of Building 802. Building 802 is a one plus-story brick facility built in 1977 with approximately 3,000 gross square feet that serves as the Fort Belvoir Community Care Unit. The building is currently used as an administrative facility also. 

Existing ceiling tiles, walls, and carpet are all in poor condition due age and wear and tear. This project was to renovate the existing facility to improve the capabilities of the facility for a new mission that has been displaced from a demolished facility. 

The work included: Demolition; Mold Remediation; Rebuild of Interior Walls and Run New Water, Sewer, and Electric Lines; Installation of New Doors; Replacement of Carpet; and Replacement of HVAC System. 

Additional work included: 

  • Inspection of the existing water line connection and replacement the line as needed. Installation of blast windows. 
  • Replacement of existing windows with blast windows. 
  • Upgrade/Installation of Fire Alarm System. 

Fort Belvoir Historic South Post Fire Station

admin November 8, 2020 Leave a reply

US Army Fort Belvoir Exterior Rehabilitation of Building 191 Historic South Post Fire Station 

The project objective was to design and rehabilitate the exterior of the South Post Fire Station Building 191 located at Fort Belvoir, Virginia. Building 191 serves as an active Fire Station for Fort Belvoir. All repairs were conducted while ensuring that Fort Belvoir’s Directorate of Emergency Services (DES) could continue to operate the building as an active Fire Station. 

Building 191 was constructed in 1934 in the Colonial-Revival architectural style. Constructed in 1943, Building 191 is a two-story, 5:1 common bond brick building. The building terminates in a hipped roof sheathed in slate shingles and rests on a poured-concrete foundation. A brick chimney is located on the south elevation. The building consists of a principal block with a pediment front incorporating a central circular window and a single-story ell. Windows general are six-over-six-light, double-hung, wood-sash units. Ornamentation consists of quoins on the north front elevation; keystones mark select openings. 

This project was for the cleaning of the building exterior, repair of damaged and failed masonry including improper past repairs; the painting and repair of wood elements such as trim, cornice, doors, entrances, and pediments; the repair of existing wood windows; cleaning and repair of concrete and stone surfaces; and the site improvements. 

The work completed under this project consisted of: stone, masonry, wood, windows, metal, foundation, and concrete repairs and replacement, painting, electrical fixture repair and replacement, and site improvements. The building exterior consisted primarily of masonry/brick construction with a concrete foundation. Architectural details, trim, and finishes were primarily wood with some metal, stone and concrete used. Lead based paints were assumed to be present on Building 191. All loose/flaking paint was removed prior to repainting. Paint chips were treated as hazardous material disposed of by the government. Special consideration of the existence of lead based paints were considered during the preparation of the painting and adequate personal protective equipment was worn. Lead paint was encapsulated. 

This project was completed under the following guidelines: 

  • Secretary of the Interior’s Standards and Guidelines for the Rehabilitation of Historic Properties
  • National Park Service, Preservation Brief #1, Assessing Cleaning and Water-Repellent Treatment for Historic Masonry Buildings
  • National Park Service, Preservation Brief #2, Reporting Mortar Joints in Historic Masonry Buildings
  • National Park Service, Preservation Brief #9, The Repair of Historic Wooden Windows
  • Fort Belvoir Directorate of Public Works Sustainable Design Elements 
  • Unified Facilities Guide Specifications (UFGS)
  • ABA Accessibility Guidelines for Building and Facilities 

The project included: 

  • Exterior Buildings Cleaning included all masonry, concrete and stone surfaces  
  • Stone and Concrete Repairs to include repairs, patching, painting and caulking of junctures between steps, ramps, landings and building foundations 
  • Wood Cornice, Eaves, Pediments, Frames and Trims Repairs 
  • Brick Repairs to include the removal of bituminous and heavy staining and paint splatter from masonry surfaces, repointed all mortar joints, brick foundations and repainted and stabilized the chimney
  • Window and Door Repairs
  • Site Work to include the installation of bollards along the western elevation parking area, removal of foundation plantings and installation of pea gravel barrier around foundation, cleaning of drain inlets, testing of functioning of subterranean drainage system and restoration to working order, replacement of missing cast iron downspout boots to include reconnection to subterranean drainage system, repair and replacement of the existing foundation well covering

Electrical and Metal Repairs to include the demolition of the existing security lights and conduits and replacement with new fixtures with interior wiring, painting of all metal railings for steps, ramps and walkways, and repair/prime/paint of all exterior metal vents and louvers.