Fort Detrick Area B

admin February 9, 2021 Leave a reply

US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick

Meltech completed this project for the US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick in Frederick, Maryland. This project was for the installation of a new 3 phase, 4-wire, electric utility distribution feeder (NDF) from Sub 6 (Area A) to Pole 1215 (Area B). 

Meltech was responsible for the engineering, furnishing, installation, and testing (EFI&T), and develop an operational scope of effort. The existing 4160v, 3 phase, 4 wire, distribution feeder (EDF) from Sub 6 to Area B was currently being operated slightly above its design limits. A project at Area B in the planning phase will require the back feeding 5 megawatts of power from Area B “back” to Area A (Sub 6). Since a new substation at Area B was not an option at this time, the NDF decided to initially operate at 4160v until a substation can be installed in the future. Knowing this, the NDF had to be designed for 34.5 kilovolt service under this effort. This will allow the Government to easily transition to the higher service voltage later. 

The project required the installation of a temporary access road through wetlands. Meltech provided a temporary wood panel road for access on and off the project site. Prior to the construction of the temporary access road, Meltech craft labor completed the transplanting of approximately 100 small trees to a temporary holding area for the course of the project for re-transplanting upon project completion. Approximately 1830 LF of 14’ wide temporary mat access road was installed on 3 individual attached impacted plates. 

Meltech provided the auger trucks for the drilling of the pole bases, approximately 80 holes for pole installation. An auger truck was used to plant the poles in the pole bases. Class II 40’-50’ treated poles were installed. After all the poles were set, we built and installed all grounds for each pole, per specification. Meltech provided a bucket truck to complete the installation of all hardware and wire. All of the poles were affixed with crossarms and insulators. Each pole differentiated with the fuse cutouts or lighting arrestors depending on requirements specified. Meltech completed the project pulling a total of (4) 3500kv new wire for each pole installation. The wires included 3 hot wires and 1 ground wire. After all wire pulling was completed and tested, Meltech performed the final termination of the wires.   

All work and materials was completed in accordance with (IAW) the latest National Electric Code (NEC), Original equipment Manufacturer (OEM) requirements, applicable Industry standards, and the SOR/SOW.

Walter Reed National Military Medical Center Tranquil Hall

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Building 62 Tranquil Hall Living Suites

The project was for interior construction, interior finishes, plumbing and selective building demolition. The project was to provide replacement ABA/ADA plumbing fixtures in Building 62 Tranquil Hall Movie Room and Gathering Place Austin’s Playroom Lobby & Warrior Café and living suites, bathrooms and at Walter Reed National Military Medical Center in Bethesda, Maryland. The work was performed on the 3rd floor basement, 2nd floor basement, 1st floor basement, and 1st floor levels.

The project required that a barrier-free design be installed in accordance with the requirements of the Federal Accessibility Standards (UFAS) as required by 42 U.S.C. 4151-4157, Architectural Barriers Act (ABA) of 1968, and consistent with 29 U.S.C. 794, Rehabilitation Act of 1973, but also had to meet the requirements of the Americans with Disabilities Act Accessibility Guidelines (ADAAG).

The fixture replacements included:

  • Removal and replacement of 35 shower/tub units
  • Removal and replacement of 153 kitchen sink faucets
  • Removal and replacement of 306 handheld shower heads (including stainless steel hoses)
  • Furnish and install 153 bidet toilet seats and associated plumbing and electrical GFI outlets to existing spare breakers (this will be installed by surface mounting plumbing and electrical inside laundry room)

Walter Reed National Military Medical Center Steam Lines

admin November 8, 2020 Leave a reply

NAVFAC Replace Steam & Condensate Piping at Walter Reed National Military Medical Center in Bethesda, Maryland

General Synopsis

Meltech completed this project for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. This project was for the replacement of the steam and condensate piping to Buildings 11, 13, 14 and 20.

The project consisted of replacing the steam and condensate piping to Buildings 11, 13, 14 & 20 for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. The project consisted of replacement of direct buried steam and condensate piping between Utility Tunnel # 5 and the Building 14 Mechanical Room along a partially new alignment and the replacement of steam and condensate piping between Building 16 and Buildings 11 and 27 along the existing Loop # 4 alignment through Manhole STML3504 and a new alignment from Manhole STML3504 to Buildings 11 and 27. The work also included the addition of a manhole to serve future Building 13 and building 20 renovations and the replacement of the Building 27 Manhole STML0304. Sequencing was required to cross connect exiting Loop #4 and Loop #7 in the basement of Building 17 prior to the start of demolition to maintain steam to buildings downstream of Manhole STML1304 during construction. The work was directly completed for Buildings 11, 13, 14 & 20 however the work was located between Buildings 14, 16, 17, 27 and 11.

Further Details

The project started with the goetech and retaining wall engineering and MOT, SCE, AGIP, SSF and portable sediment tank installation. Meltech completed the following:

  • Demolition of existing steam lines
  • Supplied, fitted and insulated approximately 340′  of 5″ SCH  40,  543′  of  3″ SCH  40  and  83′  of  2″  SCH40   black  Multi-Therm 500  direct  buried Steam pipe,
  • Supplied, fitted and insulated approximately 340′  of 3″ SCH 10 and 612′ of 3″ SCH   10 stainless Multi-Therm 500  direct  buried  condensate pipe,
  • Supplied, fitted manhole  0904 insulation of new pipe with 2″ insulation and aluminum jacket,
  • Supplied and fitted manhole  3504, new manhold North, new manhole South, Building 14, Building 11, Building 17, Building 27 insulation of new pipe with 2″ insulation  and aluminum jacket,
  • Building   27  interior  connections  to  new  steam   and  condensate lines exclude  any isolating flanges, scales pockets, condensate drain lines, shut off  valves,  check valves,  steam traps, etc. 
  • Provided   sump   pump  unit  for  new  north  and  south manhole and up to 40′ of 2″ piping to closest storm drainage     
  • Access  ladders  for  new  north  manhole,  south manhole and 3504 man holes includes vents and vent caps for new north and south manholes
  • Shop drawing  for buried pipe system (provided  by pipe manufacture)
  • Shop drawings for pipe system located in Mechanical rooms of building 11 and 14 where applicable.
  • Opening up of  valve  in  manhole   1104  after  work  in  building   11  and  17 
  • Replaced Sidewalk and Curb where demoed and Flag Pole Foundation
  • Repaired Spalding Concrete Manhole
  • Reinstallation of the Bike Rack, paving where demo’d, retaining wall across from Bldg. 17 that was demo’d and seeding and mulching of all disturbed areas.

Additional services performed included the geotechnical, concrete thermostat blocks and kickers, provided As-Built Drawings, performed the excavation and removal, welding inspections, imported the backfill materials for utilities, provided landscaping, test pits, sediment and erosion control, installation of temporary construction fence and temporary ADA compliant sidewalks, cathodic protection, sump pump installation and demolition and reinstallation of minor electric.

The main aspects of the work were:

  • Furnishing, installing and insulating approximately 340 feet of 5-inch SCH 40, 543 feet of 3-inch SCH 40, and 83 feet of 2-inch SCH 40 black Multi-Therm 500direct buried steam pipe.
  • Furnishing, installing and insulating approximately 340 feet of 3-inch SCH 10 and 612 feet of 3-inch SCH 10 stainless steel Multi-Therm 500direct buried condensate pipe.
  • Furnishing and installing a number of items, as shown on diagrams, in about one dozen manholes. All new piping to be insulated with 2 inches of insulation and aluminum jacket.
  • Furnishing and installing in Buildings 11, 13, and 14 a number of items as specified in the plans. All new piping to be insulated with 2 inches of insulation and aluminum jacket. Building 11 contained a condensate return unit.
  • Demolition of existing steam and condensate lines.
  • Connections included isolating flanges, scales pockets, condensate drain lines, shut-off valves, check valves, steam traps, etc.
  • Provide sump pumps for identifies units and up to 40 feet of piping to nearest storm drains
  • Provide access ladders, vents and vent caps for identified (on plans) manholes
  • Provide shop drawings for buried pipe system and for pipe systems located in mechanical rooms of Buildings 11 and 14
  • Maintaining strict adherence to, and “paper trail” for compliance with, the American made Act for all steel, pipe, carbon fittings, carbon valves
  • Demolition of asphalt curb and sidewalk covering areas with lines
  • Excavation the areas to install new lines
  • Demolition of old lines
  • Installation of new steam and condensate lines
  • Backfilling of trenches, installation of stone, replacing asphalt, concrete sidewalks and curbs.
  • Supplying Maintenance of Traffic for all operations including road plates
  • Excavation of areas for, and installation of, cathodic protection on newly emplaced lines
  • Final stabilization on excavated area including seed and mulch

Initial activities included:

  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection
  • Geotechnical testing

In addition there was demolition of an existing site retaining wall, and subsequent replacement of the wall (concrete wall, 7 feet high) plus provision of 30 inch wide wooden walkways.

Related work included:

  • Demolition of then-existing site retaining wall across from Building 17 and subsequent re-installation
  • Removal of flag pole with crane and subsequent reinstallation
  • Demolition of flag pole base and replacement with new base
  • Demolition of five existing light poles and associated equipment
  • New foundation and concrete for five existing light pole bases
  • Removal of bike rack, then reinstallation
  • Demolition of asphalt, curb, paving and sidewalk as appropriate with saw cutting included, and subsequent replacement
  • Supplying Maintenance of Traffic for all operations including steel road plates
  • Demolition of five trees and root pruning of two others, plus demolition of a number of bushes
  • Replacement of bushes
  • Protection of trees
  • Seeding and mulching
  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection

Walter Reed National Military Medical Center Larsons Gym

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Convert Part of Warehouse Building 226 to Auxillary Gym in Bethesda, Maryland

Meltech completed this important project for the Naval Facilities Engineering Command Washington for the conversion of part of Building 226 warehouse to an auxillary gym. This work was completed at the Walter Reed National Military Medical Center in Bethesda, Maryland.

The work consisted of the construction of interior partition walls approximately 175ft total length approximately 10.5’ high with 2×8 blocking to the north side of the existing center beam. This reduced the 50% footprint. One wall double sided approximately 40 feet in length with unfinished plywood creating a partition wall off the center of the building running east to west. The west wall was approximately 50 feet in length finished one side with unfinished plywood. The north wall approximately 24 feet in length to the light switch by the door with unfinished plywood, and the east wall from the partition wall approximately 21 feet in length to the roolup door. All plywood to be ¾” tongue and groove subfloor grade.

Meltech completed the relocation of the existing condensate drain line from the AC unit approximately 6 inches towards the rear of the building to provide clearance for the wall construction.

Meltech purchased and installed approximately 2,00 sf of interlocking rubber, “Locktuff”, flooring, minimum of ¾’ thick. Flooring was removable. The flooring installed must be able to be removed at a later date.

Smithsonian Institution Hirshhorn Museum and Sculpture Garden

admin November 8, 2020 Leave a reply

Smithsonian Institution Hirshhorn Museum and Sculpture Garden (HMSG) Supersensorial Exhibit

Meltech was awarded this Task Order through our Indefinite Delivery Indefinite Quantity Term Contract for Construction Services required by the Smithsonian Institution Museums and facilities located in the Washington DC Metro Area Mary and Virginia, plus the Smithsonian Museum facilities located in New York, NY Metropolitan area. 

This was a multi-phased project with multiple subcontractors in an occupied historical facility. Work on the project required the installation of critical elements of work which included: exhibit partitions, cutting, patching and matching of existing work, light fixtures and fire alarms. The premises were occupied during the performance of the work.  Meltech scheduled work activities to minimize interruption of occupants and occupied spaces.  

The work in the base contract included:

  • Demolition of 1275 square feet of gwb partitions
  • Construction of approximately 480 square meters (5200 square feet) of new gwb partitions
  • New construction of approximately 600 square feet of suspended gwb ceiling
  • Electrical work to provide power to artworks as shown in drawings
  • Drywall construction and finishing; wall restoration.
  • Suspended gwb ceiling construction
  • Electrical work to provide power to artworks as shown in drawings

Fort Belvoir Design Build Building 1188

admin November 8, 2020 Leave a reply

U.S. Army Mission and Installations Fort Belvoir Design Build Repair and Alterations to Building 1188 Military Clothing Store

Meltech completed this important project for the US Army Mission and Installations for the design build repair and alterations to Building 1188 at Fort Belvoir, Virginia. The Building 1188 serves as Fort Belvoir’s Military Clothing Sales store. Building 1188 is about 6,700 sf. with 4,800 sf. allotted for three NEC conference rooms and supporting requirements throughout. The work included the design build for the soundproof walls from floor to slab to bottom of the roof deck separating the projected NEC against the DMV space. Meltech created (3) VCT rooms between 300-400 sf. each with walls and ceiling at STC-45 minimum. We completed the removal of all flooring; completed installation of new carpet; provided and installed solid wood door cores with noise control device hardware; painted the new and existing wall; provided CAC card readers at entrance doors; repaired HVAC equipment for new floor layout. Meltech completed the replacement of the door lock hardware and provided and installed two X09 locks and LKM 7002 plated and installed rough-ins for ICIDS alarm system. We installed rough-ins for conference call wiring and equipment. Meltech installed new window blinds, repaired existing and installing of ceiling tile and grid and also provided and installed a water fountain with water bottle refill. 

Meltech completed the design build of the new restroom facilities to accommodate two (single use) restrooms accordingly. We also completed the design build of a small kitchenette to accommodate 4-6 users. The Kitchenette included a stainless steel sink, faucet, base and top cabinets, and a natural stone countertop/backsplash. 

Project included the complete upgrade of the fire alarm system in its entirety. 

Meltech balanced the HVAC system and equipment accordingly for the new space layout. 

Meltech upgraded the electrical panels and breakers. We also replaced and installed new LED light fixtures and wiring and switches to match the new LEDS. 

Meltech provided and installed (2) cellphone lockers in the new hallway and completed the removal of any nonbearing walls for the new floor layout configuration. 

WSSC Data Center

admin November 8, 2020 Leave a reply

Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades

Meltech was awarded this task order under our WSSC RGH Data Center Upgrades SATOC. This project was for the Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades in Laurel, Maryland. The work for this data center renovation included the following: 

  • Replacement of computer room air conditioning units in Main Computer Room and associated dry coolers and pump packages. Removal of air conditioning units in third floor PBX room and mechanical room adjacent to lake level UPS room. Replacement of ventilation fan in penthouse mechanical room.
  • New air conditioning units in PBX room and associated dry coolers and pump packages. New air conditioning units in Lake Level mechanical room to support both UPS rooms and adjacent spaces.
  • New static uninterruptible power supply, automatic transfer switch (ATS), power distribution units and panelboards to support Main Computer Room.
  • Replacement of lighting fixtures in room 3025, circuit breakers in panelboards with associated conduits, cables and other appurtenances shown on the drawings.
  • Replacement of floor tiles in the Main Computer Room and room 3025.
  • Replacement of wet pipe sprinkler system with pre-action type. Replacement of Halon fire suppression system with FM-200 system.

Fort Belvoir Design Build Community Care Unit

admin November 8, 2020 Leave a reply

US Army Design Build Renovations at Fort Belvoir Community Care Unit Building 802 at Fort Belvoir, Virginia

Meltech was awarded this project to provide all materials, labor, equipment, transportation, and services to complete the design and build and renovation of Building 802. Building 802 is a one plus-story brick facility built in 1977 with approximately 3,000 gross square feet that serves as the Fort Belvoir Community Care Unit. The building is currently used as an administrative facility also. 

Existing ceiling tiles, walls, and carpet are all in poor condition due age and wear and tear. This project was to renovate the existing facility to improve the capabilities of the facility for a new mission that has been displaced from a demolished facility. 

The work included: Demolition; Mold Remediation; Rebuild of Interior Walls and Run New Water, Sewer, and Electric Lines; Installation of New Doors; Replacement of Carpet; and Replacement of HVAC System. 

Additional work included: 

  • Inspection of the existing water line connection and replacement the line as needed. Installation of blast windows. 
  • Replacement of existing windows with blast windows. 
  • Upgrade/Installation of Fire Alarm System.