Quantico Marine Corp Base Camp Upshur

admin November 8, 2020 Leave a reply

NAVFAC Quantico Marine Corp Base Camp Upshur Water Tank Installation in Quantico, Virginia

Meltech completed this project for this NAVFAC for the installation of a Hydro-Pneumatic Tank to support the Camp Upshur water tank inspections Bldg. 2678 at Camp Upshur in Nokesville, Virginia.

Meltech completed the installation of a temporary bypass water system at Camp Upshur to allow the 100,000 gallon elevated water tank to be taken off line for inspection. Meltech set up a temporary water supply system that consisted of a 5,000 gallon hydro-pneumatic tank connected to the fire hydrant located off of Lopez Street and set the tank on the concrete area at that location. Meltech included all of the necessary piping and pressure/water relief safety valves for the temporary system. Meltech was responsible for renting/supplying the temporary fencing around the hydro-pneumatic tank during the project and the temporary water tank sanitation and perform of bacteriological sample analysis. The well pump controls at the well heads #1 & #2 were converted from water level control to a pressurized system control. The elevated water tank level data transmitted by RF telemetry signal back to the Mainside water plant was converted to a pressure reading during the project. This enabled the Mainside water plant personnel the ability to monitor the Camp Upshur water distribution system pressures during this project. Meltech charged the hydro-pneumatic tank with air at the startup of the project which was to last several weeks before becoming waterlogged. Meltech was responsible for the monitoring of the hydro-pneumatic tables air pressure and recharged when needed to ensure that the tank was functioning as designed. Meltech re-set the well head pump control back to their original settings and removed the temporary hydro-pneumatic 5,000 gallon tank, piping and fencing. This work was completed once the elevated water tank inspection was finished and the 100,000 gallon water tank was back in service and on line. Meltech supplied the hydro-pneumatic tank for 30 days after the installation and startup.

All work was completed in coordination with the customer and utilities departments. All work was completed while the water system was on line unless outages were coordinated in advance with the customer and or utilities departments.

Walter Reed National Military Medical Center Roadway Improvements

admin November 8, 2020 Leave a reply

NAVFAC Roadway Improvements at the Walter Reed National Military Medical Center – Palmer Road, South of Grier Road

General Synopsis

Meltech completed this project for the improvement of the conditions at the Robert Brown Drive and Palmer Road South Intersections at Walter Reed National Military Medical Center (WRNMMC) Naval Support Activity Bethesda (NSAB) in Bethesda, Maryland. This project was for the installation of a changeable lane assignment sign and to use an existing median as a reversible lane between South Wood Road and Building 10 East Driveway. The work was also for a construction of one west bound lane between Robert Brown Drive and Building 10 East driveway. And the last part of the construction consisted of the cutting of trees and the relocation of north sidewalk. The project objective was to have a total of three travel lanes. Two lanes were to be constructed on Palmer Road South and one lane in the off-peak direction. Meltech became familiar with the project site including any vertical and horizontal conflicts with utilities, vents, valve covers, electrical boxes, manhole covers and drainage inlets. Meltech ensured that the design and execution of the project to provide smooth transitional grades.

Further Details

The construction was based on the DoD criteria, NAVFAC Design Manuals and Criteria, ASHRAE publication including ASHRAE / IESNA Standard 90.1 Energy Standard and 62.1 Ventilation Standard, Tri-Service CADD/GIS Technology Center Standards, standard engineering and architectural practice.

The Palmer Rd South was the major east-west connection located in the southern part of the campus. It runs between Gate 2 (South Gate) on Rockville Pike all the way to the east end of the campus when it turns into University Drive. The posted speed limit on this roadway is also 20 mph. There is no on-street parking along this roadway, and except for a central left turn lane on its segment between Wood Road and Robert Brown Drive, this roadway has a two lane cross section throughout its length. It is also grade separated with Palmer Road East and forms an overpass that connects the hospital area (western part) with the university area (eastern part) of the campus. The roadway width is about 25 feet west of Stokes Road and becomes 30 feet east of it.

Geotechnical Data

Meltech was responsible for providing the services of a geotechnical engineer to conduct any subsurface exploration, investigation, testing, and analysis that the DOR deems necessary for the design and construction of the proposed facility and site improvements. Our geotechnical engineer was be registered as a Geotechnical Engineer and experienced with soil conditions in the region. The Geotechnical Engineer prepared a report addressing any elements of the work requiring his services.  The report was submitted to the Contracting Officer accompanied by a letter from the DOR certifying that the Geotechnical Engineer had reviewed the construction documents and that the design reflects the recommendations of the geotechnical report.

The project also had certain historical planning and environmental controls and protection that required our project Architect/Engineer to prepare any necessary exhibits, to attend all required presentations and obtain all necessary approvals and permits from the Maryland Department of the Environment (MOE), the Maryland State Historic Preservation Office (SHPO), and the National Capital Planning Commission (NCPC).   Meltech updated the COR, in writing, on a biweekly basis concerning the status of each permit and approval.

Design Phase

The project design was completed in compliance with the design standards and codes found in the Unified Master Reference List (UMRL) on the Whole Building Design Guide at the Unified Facilities Guide Specification (UFGS) Website. The design was provided with professional registration and design signing and stamping per requirements of UFC 1-300-09N, Design Procedures.

In accordance with Executive Order 13423, NAVFAC Engineering & Construction Bulletin (ECB) 2008-01 and other pertinent directives, integrate sustainable principles into the design, development and construction of the project. The design was to reduce the total cost of ownership of the facility using a whole building, life-cycle approach. Meltech provided integrated sustainable design strategies and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health, and comfort. Meltech provided narrative describing minimum sustainable characteristics of materials and systems used in project.

Site Improvements

Meltech provided site improvements as required to make a useable facility that meets functional and operational requirements, incorporating all applicable anti-terrorism, force protection and physical security requirements and blending into the existing environment.

The design of the pavements had to take special considerations to the anticipated traffic of cars and single unit trucks, with H2O loadings over the life of the project (20 years) as well as the existing conditions at the site. While working in and adjacent to existing pavements, Meltech matched existing adjacent finish elevation, materials, paving section and texture. We provide pavement design and pavement section materials in accordance with UFC 3-200-10N, Civil Engineering.

Roadways of bituminous pavement or rigid pavement were not authorized. Meltech provided curb and gutter to tie into the adjacent facilities. Meltech also provided resurfacing of existing pavement by slurry seal/bituminous surface treatments/bituminous overlays. We also provided any other roadway improvements such as bus stops, traffic signalization, markings, signage to match the existing, guardrails, wheel stops and bollards. Meltech provided a network of Portland cement concrete sidewalks, separated from, but connected to vehicular circulation systems, to all pedestrian and vehicle access.

All the site furnishings conformed to the Base Installation Appearance Plan (BIAP) and the Installation and Appearance Guide. The Director of Records found that there was no need for a storm water management facility however we did relocate an existing Stormwater management structure to open up the roadways.

Traffic Control

Meltech coordinated with the Facility Traffic Engineer and Safety Office, propose and obtain approval for traffic control measures that may be required in performance of the work required by the contract.

Performance Verification and Acceptance Testing

  1. Subgrade Preparation: Proof rolling was performed in the presence of the Contracting Officer. Rutting or pumping of material was undercut as directed by the Contracting Officer and replaced with satisfactory soil materials as defined by the Geotechnical Engineer.
  2. Base Course Performance Verification: Meltech performed visual performance verification. Surfaces were to smooth with no ruts, sloped or crowned to not pond water.
  3. Bituminous Concrete Pavement Performance Verification: Meltech performed visual performance verification. Finished surface were to be uniform in texture and appearance, free of defects such as cracks and creases, and be sloped or crowned so as to not pond water.
  4. Portland Cement Concrete Pavement Performance Verification: At a minimum, Meltech performed visual performance verification. Finished surface shall be uniform in texture and appearance, free of defects such as cracks and spalls, and be sloped or crowned so as to not pond water.
  5. Concrete Joint Performance Verification: Joint sealer that fails to cure properly, or fails to bond to joint walls, or reverts to uncured state or fails in cohesion, or shows excessive air voids, blisters, or has surface defects, swells, or other deficiencies, or is not recessed within indicated tolerances shall be rejected.  Removed any rejected sealer, re-cleaned and resealed joints.

Substructure Foundation

Foundations were reinforced on concrete slabs-on-grade with continuous strip footings or isolated spread footings. Concrete slabs were not less than 4-inches in thickness and footings weren’t less than 18 inches below the lowest adjacent grade.  Foundations were designed and constructed of reinforced concrete.  All design and construction complied with IBC and with applicable requirements in Section B Shell. 

Painting

Meltech provided a minimum of one prime coat and two finish coats. The prime coat was not be combined with texture or other coatings. Meltech sealed and primed all surfaces to cover underlying stains or discoloration that may affect finish paint. Finish coats provided full coverage of undercoats and substrates. Meltech provided Institutional Low Odor/Low VOC Latex paint or High Performance Architectural Latex systems as defined and approved by the MPI Systems Manual for the various substrates required to be painted. We also provide paint systems tested to “Detailed Performance Level” standard as defined by MPI. 

Site Earthwork

Meltech provided grading so the site would drain with smooth transitions to surround grading and storm drain inlets.  We adjusted the heights of existing drain inlets and manholes to provide smooth grades. Blasting for rock excavation was not permitted. All unsuitable material and surplus excavation became the property of Meltech and was disposed of off Government property.

Utilities

  • Provided temporary utilities which included any equipment needed for temporary utility tie-ins, permanent utility systems, telephone and data service, installed and certified back flow preventers on all connections to the potable water supply systems
  • Provided documentation that all life safety and fire protection features and systems were installed
  • Verified on-site utilities and had them marked out by a utility locator service prior to the start of construction. Existing piping, utilities, oil and gas lines, and underground obstructions of any type that were to remain were indicated in locations to be traversed by new piping, ducts, and other work provided herein, and such were not indicated or specified to be removed, the elevations of the existing utilities and obstructions were be determined before the new work was laid closer than the nearest manhole or other structure at which an adjustment in grade was made. 
  • Obtain required dig permits and notify the Contracting Officer 21 calendar days prior to any excavation. 
  • Utilities   located within concrete slabs are extremely difficult to identify due to the reinforcing steel used in the construction of these structures; whenever work involved concrete chipping, saw cutting, or core drilling, the existing utility location was coordinated with station utility departments in addition to a private locating service.
  • Outages to isolate utility systems were used in circumstances where utilities are unable to be positively identified. 

Warranty and Record Drawings and Operation & Maintenance (O&M) Data

The project required that Meltech warrant all materials and work for not less than one year after final acceptance of the work. Meltech agreed to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair, if required.  For warranted items, Meltech furnished the manufacturers’ original written warranty accompanied by a copy of the supplier’s receipt showing place of purchase, telephone number of supplier, address, delivery order and ticket number. Meltech also warranted all woody plant materials for a period of one year from acceptance by the Government.  Meltech warranted all perennial plants and turf grass for one complete growing season. The Government accepted no responsibility for plant material maintenance during the warranty period except for periodic turf grass mowing. If the plant exhibits 25% or greater dieback, the plants were considered dead and were replaced in-kind and of the same size, with no additional cost to the Government. The replacement plants were maintained and warranted by Meltech for one additional complete growing season at no additional cost to the government. If the replacement plant died Meltech credited the Government the full installed price of the plant. All turf grass areas that fail to exhibit a healthy coverage of turf grass after one complete growing season was also re-seeded or re-sodded until a satisfactory turf grass area was established.

Meltech furnished the hard copies and electronic format for all the as-built and O&M information.  The record drawings incorporated all the changes to the approved final design.   We provided O&M data for as-built products, materials, and equipment,  including  data  sheets,  test  reports, warranties,  certificates,  list  of  spare  parts suppliers for all pieces of equipment, and approved construction submittals.

Budget Management

This project required a Budget Management System to be developed and maintained. The Budget Management System represented the major portions of the work. The purpose of budget management was to balance scope and value during critical project design decisions. The project manager updated the budget management status at regular intervals during design for review by and discussion with the COR. The final budget management summary corresponded with the final Schedule of Prices.

Fort Leonardwood

admin November 8, 2020 Leave a reply

US Army Corps of Engineers Mobile District Fort General Leonard Wood Community Hospital Modular Clinic Site Work in Fort Leonard Wood, MO

This project was result of a MEDCOM CONUS wide contract administered by the U.S. Army Corps of Engineers, Mobile District. Meltech completed this project for the development of a work plan and drawings which detailed all site utilities work, grading and tie-ins.  Modular clinic drawings provided floor plans and utilities layouts, including distribution and load estimates. Work plan also defined all the required outages to electrical and plumbing utilities; and identified all invasive utilities and civil work outside the existing buildings adjacent to the planned clinic. The option that was awarded shortly after was for the complete supply and installation of a new and completely functional Modular Medical Clinic that meet all Local, State, and Federal medical standards and codes.

Fort Detrick and Forest Glen Occupancy Sensors

admin November 8, 2020 Leave a reply

U.S. Army Corps of Engineers Baltimore District Frederick National Laboratory of Cancer Research (FNLCR) Occupancy Sensors, 200 kWPV, and Thermostats at Fort Detrick in Frederick, MD and Forest Glen Annex, Maryland

This project was for the installation of occupancy sensors at the Fort Detrick and Forest Glen Annex for the reduction of energy usage garrison wide through the use of occupancy sensors and modified boiler controls. The projects objectives were to reduce energy usage garrison wide through the use of occupancy sensors and modified boiler controls by providing roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels installed on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material.

The existing roofing system and its attachment to the existing structural roof framing system were evaluated and modified, to support the 200 kW roof mounted PV system. Meltech provided modifications to the existing roof system design and construction for the entire facility roof system, and including all necessary ancillary and incidental work necessary to maintain a watertight roof system installation while allowing for the installation of the 200 kW roof mounted PV system. We coordinated with system manufacturer to maintain existing system warranty. We followed all manufactures written recommendations and recertified the roof following construction.

We provided a roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels were provided on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material. The project consisted of three distinct parts: installation of occupancy sensors in 27 different buildings throughout the base and one at the Forest Glen Annex, installation of a roof mounted solar array on Building 693, and modifications to two boiler control sequences in Building 1532. Various types of occupancy sensors were utilized based on the construction and configurations of the rooms in which the lighting fixtures are going to be controlled. A blend of wall mounted, ceiling mounted, wireless, line voltage, and low voltage sensors were used. The buildings have were surveyed and the most beneficial and cost effective occupancy sensor applications were been identified. Wireless occupancy sensors were designated where wired sensors would result in significant architectural wall repair and disruption during construction. Low voltage sensors with power packs were specified where the coverage of multiple occupancy sensors to control one lighting circuit was required. Line voltage ceiling mounted sensors were provided where exposed conduit and conductors make interception of existing circuits a relatively simple matter. Wall mounted switch type occupancy sensors were provided in private office and other small rooms where existing switches can be replaced in existing outlet boxes to achieve appropriate coverage. Meltech provided modifications to existing area lighting systems consisting of fluorescent, metal halide, and incandescent, lighting to include occupancy sensors for automatic shut-off of fixtures in unoccupied spaces.

The work was completed on the following buildings:

Bldg. 243 – Bacteriology Lab
Bldg. 374 – Greenhouse Facility Lab
Bldg. 810 – Headquarters
Bldg. 1077 – CDMRP Building
Bldg. 1405 – AAFES / Post Exchange (Mini Mall) PX/Military Clothing
Bldg. 1430 – Unaccompanied Enlisted Personnel Housing
Bldg. 1529 – Community Activities Center
Bldg. 1533 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1534 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1535 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1536 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1538 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1540 – Certification Testing Information Assurance Training Center
Bldg. 1541 – Civilian Personnel Advisory Center
Bldg. 1545 – Administrative Offices
Bldg. 1546 – Administrative Offices
Bldg. 1674 – Procurement Division Building

 

 


Fort McNair National Defense University

admin November 8, 2020 Leave a reply

US Army Corps of Engineers National Defense University Fort McNair Marshall Hall South Plaza in Washington, DC

General Synopsis 

Meltech completed this important project for the US Army Corps of Engineers Baltimore District for the National Defense University George Marshall Hall at Fort Lesley J. McNair in Washington, DC. The project included the demolition, construction and landscaping (with environmental aspects) in the South Plaza immediately adjacent to Marshall Hall. 

In length of service as an Army post, Fort McNair ranks third and is the home of the National Defense University (NDU). Marshall hall is part of NDU and operations continued uninterrupted at the building throughout the project.

Meltech’s contract consisted of a two-part base bid. The first part of the base bid was for the demolition of concrete paving, utilities, plants, and all other demolition-related site work as shown on plans and specified. The second part of the base bid consisted of construction of an extended sidewalk and re-planting in the area west of 5th Avenue, and other related construction on the Marshall Hall South Plaza together with surrounding landscaping and storm-water management construction.

Since 90% of the buildings on Fort McNair’s 100 acres are historic buildings (built, reconstructed or remodeled prior to 1908) Meltech’s work was, as with that at Arlington National Cemetery above, subject to extremely vigilant oversight by the U.S. Army Corps of Engineers. For example, backfill materials had to be placed adjacent to all types of structures, and compacted to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, in order to prevent wedging action or eccentric loading upon or against the structure. Compaction had to be finished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Similarly the placement and treatment of bedding, graded stone, various sands and gravels and other fill materials, was strictly controlled and overseen. 

Further Details 

Divisional work associated with the base bid included:

  • Division 2 work consisted of demolition, deconstruction, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work, placement of select fill and topsoil layers for landfill cover systems on geosynthetic materials.
  • Division 3 work consisted of cast-in-place concrete, precast concrete wall panels with normal-weight aggregate Portland cement concrete, conventional reinforcing, and smooth surface or exposed aggregate facing 
  • Division 4 work consisted of reinforced and non-reinforced masonry.
  • Division 7 work consisted of applying sealants for normal building construction.
  • Division 10 work (Specialties) consisted of a pre-manufactured fabric covered steel shelter structure and vertical metal treillage device that allows for plant and vine support. 
  • Division 12 work consisted of miscellaneous site and street furniture and furnishings including shelters, waste and recycle receptacles, ash urns, tables, and chairs. 
  • Division 26 work consisted of general electrical work at the site, installation of photoconductive lighting control devices for use with exterior lighting systems, and installation of exterior lighting systems.
  • Division 31work consisted of earthwork activities, clearing and disposal of trees, stumps, clearing fences, buildings, and other structures and disposal of debris, trash, and materials resulting from clearing operations, clearing and grubbing.
  • Division 32 work consisted of plant material and irrigation during the establishment 
  • Period, concrete sidewalks and curbs and gutters, constructing a concrete block pavement, seeding, exterior planting, storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), and polyethylene (PE) pipe, sub-drainage systems for drainage of water from under the ground.

 

Meltech received an outstanding performance evaluation for the base bid work and as a result two further optional items were exercised. The first option item was for supply and installation of “Bioswale plantings”, procuring and replacing an electrical manhole ring, refinishing some existing structural elements, and addition of a ground neutral line in the panel box feeding the lights and outlets on the site. Bioswales are landscape elements designed to remove silt and pollution from surface runoff water. They consist of a swaled drainage course with gently sloped sides (less than six percent) and filled with vegetation, compost and/or riprap.  The water’s flow path, either a meandering or almost straight, with wide and shallow ditches, maximizes the time water spends in the swale, thus trapping pollutants and silt. Biological factors also contribute to the breakdown of certain pollutants. This work involved a modification to provide and install an extension of the existing irrigation sprinkler system to two new areas adjacent to the South Plaza and Bioswale. 

The second option item involved the supply and installation of exterior furniture at the site. The major scope elements of the options work were:

  1. Field investigation and measurements for the work
  2. Preconstruction/technical/product submittals and shop drawings
  3. Rigging and hoisting for the work
  4. Protection of existing surfaces
  5. Coordination with other trades
  6. Layout for the work
  7. Site demolition as necessary
  8. Third party testing of the work
  9. Provision of full-time on-site superintendent
  10. Daily cleanup of all trash and debris generated by the work
  11. Hauling and removal of all trash and debris
  12. Coordination, inspection and identification of underground utilities
  13. Furnishing and installing all erosion and sediment control systems
  14. Furnishing and installing all tree protection
  15. Furnishing and installing inlet protection
  16. Furnishing and installing a stabilized construction entrance 
  17. Furnishing and installing all concrete sidewalks, seat walls and footers
  18. Furnishing and installing all paver systems
  19. Furnishing and installing striping
  20. Furnishing and installing all plantings including shrubs  and trees
  21. Furnishing and installing all seeding
  22. All rough and fine grading
  23. Furnishing and installing all perforated under-drain piping
  24. Furnishing and installing all rip-rap and miscellaneous stone
  25. Furnishing and installing all mulch
  26. Ancillary support (permits, licenses, Davis-Bacon, certified payrolls, applic. taxes, etc.)

 

WSSC Potomac Water Filtration Plant

admin November 8, 2020 Leave a reply

Washington Suburban Sanitary Commission (WSSC) Construction Services at the Potomac Water Filtration Plant (WFP) Outdoor Substation 2 for existing 5kV Switchgear

Meltech completed this project was for the Washington Suburban Sanitary Commission (WSSC) Construction Services at the Potomac Water Filtration Plant (WFP). This project was for construction services to the Outdoor Substation 2 for existing 5kV Switchgear. The work on this project consisted of the installation of an outdoor entrance landing, stairs and elevated HVAC platform and chain link fence modifications at the Potomac Water Filtration Plan (WFP) Outdoor Substation 2 for existing 5kV Switchgear. Meltech also provided temporary chain link fence and gates where required for protection of work.

WSSC Data Center

admin November 8, 2020 Leave a reply

Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades

Meltech was awarded this task order under our WSSC RGH Data Center Upgrades SATOC. This project was for the Washington Suburban Sanitary Commission (WSSC) Richard G. Hocevar (RGH) Building Data Center Upgrades in Laurel, Maryland. The work for this data center renovation included the following: 

  • Replacement of computer room air conditioning units in Main Computer Room and associated dry coolers and pump packages. Removal of air conditioning units in third floor PBX room and mechanical room adjacent to lake level UPS room. Replacement of ventilation fan in penthouse mechanical room.
  • New air conditioning units in PBX room and associated dry coolers and pump packages. New air conditioning units in Lake Level mechanical room to support both UPS rooms and adjacent spaces.
  • New static uninterruptible power supply, automatic transfer switch (ATS), power distribution units and panelboards to support Main Computer Room.
  • Replacement of lighting fixtures in room 3025, circuit breakers in panelboards with associated conduits, cables and other appurtenances shown on the drawings.
  • Replacement of floor tiles in the Main Computer Room and room 3025.
  • Replacement of wet pipe sprinkler system with pre-action type. Replacement of Halon fire suppression system with FM-200 system.

Fort Belvoir Design Build Community Care Unit

admin November 8, 2020 Leave a reply

US Army Design Build Renovations at Fort Belvoir Community Care Unit Building 802 at Fort Belvoir, Virginia

Meltech was awarded this project to provide all materials, labor, equipment, transportation, and services to complete the design and build and renovation of Building 802. Building 802 is a one plus-story brick facility built in 1977 with approximately 3,000 gross square feet that serves as the Fort Belvoir Community Care Unit. The building is currently used as an administrative facility also. 

Existing ceiling tiles, walls, and carpet are all in poor condition due age and wear and tear. This project was to renovate the existing facility to improve the capabilities of the facility for a new mission that has been displaced from a demolished facility. 

The work included: Demolition; Mold Remediation; Rebuild of Interior Walls and Run New Water, Sewer, and Electric Lines; Installation of New Doors; Replacement of Carpet; and Replacement of HVAC System. 

Additional work included: 

  • Inspection of the existing water line connection and replacement the line as needed. Installation of blast windows. 
  • Replacement of existing windows with blast windows. 
  • Upgrade/Installation of Fire Alarm System. 

Fort Detrick Building 1021

admin November 8, 2020 Leave a reply

Leidos Biomedical Research Inc. Frederick National Laboratory for Cancer Research (FNLCR) New Utilities to Serve New Animal Watering System at Building 1021 at Fort Detrick, MD

Meltech completed this project for the Leidos Biomedical Research Inc. Frederick National Laboratory for Cancer Research (FNLCR) new utilities to serve the new animal water system at Building 1021 at Fort Detrick in Frederick, Maryland. 

The project included the: 

  • Installation of new NCW supply piping including backflow preventers, pressure reducing valve, water hammer arrestor, etc. 
  • Installation of power including outlets, disconnects, junction boxes, etc.
  • Installation of floor sink and drain pipe
  • Relocations of emergency shower and installation of mixing valve
  • Excavation for new AWS and AWR piping across roadway. Installation of AWS and AWR piping into Building 1021. 
  • Patching and repair of roadway and curbing. 
  • Excavation at existing AWR piping capped to remove existing animal watering system from loop
  • Installation of new animal watering system in Building 1021
  • Connection of animal watering system to Meltech installed NCW, Power AWS and AWR piping 
  • Installation of animal watering bagging system piping 
  • Start-up and sanitization of system
  • Brief animal watering system shut-down scheduled to perform tie in of the new animal watering system into the existing loop piping. During the shut-down the existing animal watering system was taken out of service and the existing piping capped. 
  • Backfill of excavated areas and restoration to original conditions
  • Railing system installation around new animal watering system
  • Installation of quartz topcoat with cove base 
  • Moisture remediation of concrete floor patching 
  • Window tinting to mitigate potential impact of sunlight in the translucent tank room