Walter Reed National Military Medical Center Tranquil Hall

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Building 62 Tranquil Hall Living Suites

The project was for interior construction, interior finishes, plumbing and selective building demolition. The project was to provide replacement ABA/ADA plumbing fixtures in Building 62 Tranquil Hall Movie Room and Gathering Place Austin’s Playroom Lobby & Warrior Café and living suites, bathrooms and at Walter Reed National Military Medical Center in Bethesda, Maryland. The work was performed on the 3rd floor basement, 2nd floor basement, 1st floor basement, and 1st floor levels.

The project required that a barrier-free design be installed in accordance with the requirements of the Federal Accessibility Standards (UFAS) as required by 42 U.S.C. 4151-4157, Architectural Barriers Act (ABA) of 1968, and consistent with 29 U.S.C. 794, Rehabilitation Act of 1973, but also had to meet the requirements of the Americans with Disabilities Act Accessibility Guidelines (ADAAG).

The fixture replacements included:

  • Removal and replacement of 35 shower/tub units
  • Removal and replacement of 153 kitchen sink faucets
  • Removal and replacement of 306 handheld shower heads (including stainless steel hoses)
  • Furnish and install 153 bidet toilet seats and associated plumbing and electrical GFI outlets to existing spare breakers (this will be installed by surface mounting plumbing and electrical inside laundry room)

Walter Reed National Military Medical Center Steam Lines

admin November 8, 2020 Leave a reply

NAVFAC Replace Steam & Condensate Piping at Walter Reed National Military Medical Center in Bethesda, Maryland

General Synopsis

Meltech completed this project for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. This project was for the replacement of the steam and condensate piping to Buildings 11, 13, 14 and 20.

The project consisted of replacing the steam and condensate piping to Buildings 11, 13, 14 & 20 for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. The project consisted of replacement of direct buried steam and condensate piping between Utility Tunnel # 5 and the Building 14 Mechanical Room along a partially new alignment and the replacement of steam and condensate piping between Building 16 and Buildings 11 and 27 along the existing Loop # 4 alignment through Manhole STML3504 and a new alignment from Manhole STML3504 to Buildings 11 and 27. The work also included the addition of a manhole to serve future Building 13 and building 20 renovations and the replacement of the Building 27 Manhole STML0304. Sequencing was required to cross connect exiting Loop #4 and Loop #7 in the basement of Building 17 prior to the start of demolition to maintain steam to buildings downstream of Manhole STML1304 during construction. The work was directly completed for Buildings 11, 13, 14 & 20 however the work was located between Buildings 14, 16, 17, 27 and 11.

Further Details

The project started with the goetech and retaining wall engineering and MOT, SCE, AGIP, SSF and portable sediment tank installation. Meltech completed the following:

  • Demolition of existing steam lines
  • Supplied, fitted and insulated approximately 340′  of 5″ SCH  40,  543′  of  3″ SCH  40  and  83′  of  2″  SCH40   black  Multi-Therm 500  direct  buried Steam pipe,
  • Supplied, fitted and insulated approximately 340′  of 3″ SCH 10 and 612′ of 3″ SCH   10 stainless Multi-Therm 500  direct  buried  condensate pipe,
  • Supplied, fitted manhole  0904 insulation of new pipe with 2″ insulation and aluminum jacket,
  • Supplied and fitted manhole  3504, new manhold North, new manhole South, Building 14, Building 11, Building 17, Building 27 insulation of new pipe with 2″ insulation  and aluminum jacket,
  • Building   27  interior  connections  to  new  steam   and  condensate lines exclude  any isolating flanges, scales pockets, condensate drain lines, shut off  valves,  check valves,  steam traps, etc. 
  • Provided   sump   pump  unit  for  new  north  and  south manhole and up to 40′ of 2″ piping to closest storm drainage     
  • Access  ladders  for  new  north  manhole,  south manhole and 3504 man holes includes vents and vent caps for new north and south manholes
  • Shop drawing  for buried pipe system (provided  by pipe manufacture)
  • Shop drawings for pipe system located in Mechanical rooms of building 11 and 14 where applicable.
  • Opening up of  valve  in  manhole   1104  after  work  in  building   11  and  17 
  • Replaced Sidewalk and Curb where demoed and Flag Pole Foundation
  • Repaired Spalding Concrete Manhole
  • Reinstallation of the Bike Rack, paving where demo’d, retaining wall across from Bldg. 17 that was demo’d and seeding and mulching of all disturbed areas.

Additional services performed included the geotechnical, concrete thermostat blocks and kickers, provided As-Built Drawings, performed the excavation and removal, welding inspections, imported the backfill materials for utilities, provided landscaping, test pits, sediment and erosion control, installation of temporary construction fence and temporary ADA compliant sidewalks, cathodic protection, sump pump installation and demolition and reinstallation of minor electric.

The main aspects of the work were:

  • Furnishing, installing and insulating approximately 340 feet of 5-inch SCH 40, 543 feet of 3-inch SCH 40, and 83 feet of 2-inch SCH 40 black Multi-Therm 500direct buried steam pipe.
  • Furnishing, installing and insulating approximately 340 feet of 3-inch SCH 10 and 612 feet of 3-inch SCH 10 stainless steel Multi-Therm 500direct buried condensate pipe.
  • Furnishing and installing a number of items, as shown on diagrams, in about one dozen manholes. All new piping to be insulated with 2 inches of insulation and aluminum jacket.
  • Furnishing and installing in Buildings 11, 13, and 14 a number of items as specified in the plans. All new piping to be insulated with 2 inches of insulation and aluminum jacket. Building 11 contained a condensate return unit.
  • Demolition of existing steam and condensate lines.
  • Connections included isolating flanges, scales pockets, condensate drain lines, shut-off valves, check valves, steam traps, etc.
  • Provide sump pumps for identifies units and up to 40 feet of piping to nearest storm drains
  • Provide access ladders, vents and vent caps for identified (on plans) manholes
  • Provide shop drawings for buried pipe system and for pipe systems located in mechanical rooms of Buildings 11 and 14
  • Maintaining strict adherence to, and “paper trail” for compliance with, the American made Act for all steel, pipe, carbon fittings, carbon valves
  • Demolition of asphalt curb and sidewalk covering areas with lines
  • Excavation the areas to install new lines
  • Demolition of old lines
  • Installation of new steam and condensate lines
  • Backfilling of trenches, installation of stone, replacing asphalt, concrete sidewalks and curbs.
  • Supplying Maintenance of Traffic for all operations including road plates
  • Excavation of areas for, and installation of, cathodic protection on newly emplaced lines
  • Final stabilization on excavated area including seed and mulch

Initial activities included:

  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection
  • Geotechnical testing

In addition there was demolition of an existing site retaining wall, and subsequent replacement of the wall (concrete wall, 7 feet high) plus provision of 30 inch wide wooden walkways.

Related work included:

  • Demolition of then-existing site retaining wall across from Building 17 and subsequent re-installation
  • Removal of flag pole with crane and subsequent reinstallation
  • Demolition of flag pole base and replacement with new base
  • Demolition of five existing light poles and associated equipment
  • New foundation and concrete for five existing light pole bases
  • Removal of bike rack, then reinstallation
  • Demolition of asphalt, curb, paving and sidewalk as appropriate with saw cutting included, and subsequent replacement
  • Supplying Maintenance of Traffic for all operations including steel road plates
  • Demolition of five trees and root pruning of two others, plus demolition of a number of bushes
  • Replacement of bushes
  • Protection of trees
  • Seeding and mulching
  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection

Walter Reed National Military Medical Center Larsons Gym

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Convert Part of Warehouse Building 226 to Auxillary Gym in Bethesda, Maryland

Meltech completed this important project for the Naval Facilities Engineering Command Washington for the conversion of part of Building 226 warehouse to an auxillary gym. This work was completed at the Walter Reed National Military Medical Center in Bethesda, Maryland.

The work consisted of the construction of interior partition walls approximately 175ft total length approximately 10.5’ high with 2×8 blocking to the north side of the existing center beam. This reduced the 50% footprint. One wall double sided approximately 40 feet in length with unfinished plywood creating a partition wall off the center of the building running east to west. The west wall was approximately 50 feet in length finished one side with unfinished plywood. The north wall approximately 24 feet in length to the light switch by the door with unfinished plywood, and the east wall from the partition wall approximately 21 feet in length to the roolup door. All plywood to be ¾” tongue and groove subfloor grade.

Meltech completed the relocation of the existing condensate drain line from the AC unit approximately 6 inches towards the rear of the building to provide clearance for the wall construction.

Meltech purchased and installed approximately 2,00 sf of interlocking rubber, “Locktuff”, flooring, minimum of ¾’ thick. Flooring was removable. The flooring installed must be able to be removed at a later date.

Walter Reed National Military Medical Center Bowling Alley

admin November 8, 2020 Leave a reply

NAVFAC Bethesda Bowling Alley

Meltech completed this important project for the Naval Facilities Engineering Commanf Washington at the Walter Reed National Military Medical Center Bowling Alley. This project was for the backfill, compact and plant sod over a low area by the deck of the bowling alley, Building 56, at the National Support Activity, Bethesda, Maryland.

The work was completed on the east side of the outside deck of the Bowling Alley, Building 56. Meltech filled in the low area, compacted the soil and placed sod over the newly placed soil.

Fort Leonardwood

admin November 8, 2020 Leave a reply

US Army Corps of Engineers Mobile District Fort General Leonard Wood Community Hospital Modular Clinic Site Work in Fort Leonard Wood, MO

This project was result of a MEDCOM CONUS wide contract administered by the U.S. Army Corps of Engineers, Mobile District. Meltech completed this project for the development of a work plan and drawings which detailed all site utilities work, grading and tie-ins.  Modular clinic drawings provided floor plans and utilities layouts, including distribution and load estimates. Work plan also defined all the required outages to electrical and plumbing utilities; and identified all invasive utilities and civil work outside the existing buildings adjacent to the planned clinic. The option that was awarded shortly after was for the complete supply and installation of a new and completely functional Modular Medical Clinic that meet all Local, State, and Federal medical standards and codes.