Fort Detrick Area B

admin February 9, 2021 Leave a reply

US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick

Meltech completed this project for the US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick in Frederick, Maryland. This project was for the installation of a new 3 phase, 4-wire, electric utility distribution feeder (NDF) from Sub 6 (Area A) to Pole 1215 (Area B). 

Meltech was responsible for the engineering, furnishing, installation, and testing (EFI&T), and develop an operational scope of effort. The existing 4160v, 3 phase, 4 wire, distribution feeder (EDF) from Sub 6 to Area B was currently being operated slightly above its design limits. A project at Area B in the planning phase will require the back feeding 5 megawatts of power from Area B “back” to Area A (Sub 6). Since a new substation at Area B was not an option at this time, the NDF decided to initially operate at 4160v until a substation can be installed in the future. Knowing this, the NDF had to be designed for 34.5 kilovolt service under this effort. This will allow the Government to easily transition to the higher service voltage later. 

The project required the installation of a temporary access road through wetlands. Meltech provided a temporary wood panel road for access on and off the project site. Prior to the construction of the temporary access road, Meltech craft labor completed the transplanting of approximately 100 small trees to a temporary holding area for the course of the project for re-transplanting upon project completion. Approximately 1830 LF of 14’ wide temporary mat access road was installed on 3 individual attached impacted plates. 

Meltech provided the auger trucks for the drilling of the pole bases, approximately 80 holes for pole installation. An auger truck was used to plant the poles in the pole bases. Class II 40’-50’ treated poles were installed. After all the poles were set, we built and installed all grounds for each pole, per specification. Meltech provided a bucket truck to complete the installation of all hardware and wire. All of the poles were affixed with crossarms and insulators. Each pole differentiated with the fuse cutouts or lighting arrestors depending on requirements specified. Meltech completed the project pulling a total of (4) 3500kv new wire for each pole installation. The wires included 3 hot wires and 1 ground wire. After all wire pulling was completed and tested, Meltech performed the final termination of the wires.   

All work and materials was completed in accordance with (IAW) the latest National Electric Code (NEC), Original equipment Manufacturer (OEM) requirements, applicable Industry standards, and the SOR/SOW.

Federal Bureau of Investigations Criminal Justice Information Service Division Complex

admin November 8, 2020 Leave a reply

Federal Bureau of Investigations (FBI) Criminal Justice Information services (CJIS) Division Complex Campus Paving, Repair and Maintenance in Clarksburg, West Virginia 

Meltech completed this project for the Federal Bureau of Investigations (FBI) Criminal Justice Information Services (CJIS) Division Complex Campus Paving, Repair and Maintenance project in Clarksburg, West Virginia. 

This work was completed on the CJIS Campus. The campus location is on approximately 35 acres of asphalt pavement that includes parking areas, roadways, docks, access driveways and walking paths. The site pavement is original to its construction in 1993-1994. Multiple areas of exposed coarse aggregate with noticeable spider cracks throughout the wearing course were identified in this project for repair. The roadway from the East Gate to the Child Development Center (CDC) also had visible cracking along the cold joints where the original paving passes stopped and started. The shoulders along this road were eroded and also required restoration. Several drop inlets (drains) had identified failing concrete basins that required repair to continue proper drainage of the parking lots. The concrete damage posed safety concerns for the campus and required repairs in order to ensure safe activities in the area. 

Meltech developed a work plan and method of execution for the work in accordance with the design package. The work plan included a schedule, phasing plan, submittals, QC Plan, Traffic Control plan, Asphalt Testing plan and a Millings Disposal plan. Each plan submitted required approval prior to construction. The project also required several safety plans prior to start. Meltech management worked directly with our safety department to complete the Environmental Protection Plan, Accident and Prevention Plan (APP), Activity Hazard Analysis (AHA), Crane Critical Lift Plan with proof of qualification for crane operators, Indoor Air Quality Management Plan (IAQ), Construction Site Plan, Traffic Control plan, Waste Management Plan, 

The work included approximately 67,220 sq. yds. of repair work. Majority of the work was concentrated on the wearing course. The wearing coursed required 1-1/2” to 2” to be milled and overlaid with 1-1/2” to 2” of new asphalt. A total of 6 catch basins were identified for repairs. There was approximately 2460 SF of full depth repair and other miscellaneous repairs completed with the project package. 

Understanding the work identified in this project as asphalt repair, Meltech immediately recognized the need to complete this work prior to the start of winter. This project was completed for multiple parking lots, access drives, walking paths and other areas of occupancy. Being an occupied facility Meltech understood the work had to be coordinated with the daily activities of the campus. With these considerations in mind, Meltech submitted a fast-tracked schedule to complete the work in after hours, weekends and in double shift. This work was completed in half the time and included 2 additional modifications for an addition of shoulder stone and other miscellaneous items; for a contract completion of an entire 6 months early.  

Federal Bureau of Investigations J. Edgar Hoover Headquarters Design Build

admin November 8, 2020 Leave a reply

Federal Bureau of Investigations (FBI) Design Build Construction Services for the Courtyard Renovations at the J Edgar Hoover FBI Building Headquarters in Washington, DC

This project was for the Federal Bureau of Investigations (FBI) Design Build Construction Services for the Courtyard Renovations at the J Edgar Hoover Headquarters in Washington, DC. The current courtyard has become a safety hazard. Employees and visitors have begun complaining of trip hazards, and pools of standing water (which freeze in the winter). The standing water and poor drainage of the courtyard are causing leaks in the ceiling below the courtyard, leading to displacement of employees, damage of equipment, and some instances of mold/mildew. Finally, the stairs that lead to the second floor are beginning to deteriorate to the point where foot traffic is being impeded. Due to the safety and health issues caused by the J. Edgar Hoover Building’s courtyard disrepair, the FBI was seeking options for repair solutions to make safe the courtyard and stairs, as well as address the poor drainage of the area.

This project was to provide the FBI a conceptual drawing of three (3) options for executive decision-making and to repair the courtyard area to include the removal of the failing pavers, waterproofing of the structural slab, repair or replacement of the courtyard stairs (based on structural survey), and installation of proper drainage for the courtyard area to eliminate pooling of water. The courtyard must drain properly in heavy rains, provide a safe walking area for employees, and provide a parking/turnaround area for visiting Distinguished Visitors’ (DV’s) vehicles (up to 3 armored Sport Utility Vehicles (SUVs).

The project required Meltech to perform site investigation, investigation of options, development of design concepts and production of an investigation report, including a discussion of options with recommendations and cost estimates. Meltech provided three (3) options for the courtyard repair and improvement.

The options provided were:

  1. Replacement of the surface in kind. This option included the work identified above, and included the phased reinstallation of granite cobbles (maximization of cobble re-use) in a “Wishbone” or “Roman Cobble” pattern (as currently exists). All cobbles were grouted and sealed to repel and direct water to the drains.
  2. Replacement of the surface with a stamped concrete or equivalent surface. This option included the work identified above, and included the phased installation of a surface that met the project objectives.
  3. Replacement of the existing surface with a combination of an installation of landscaping/greenspace features with a structural surface as described in the first and second options. This option includes the work identified above, and also accommodated pedestrian and limited vehicular traffic. The greenspace design included paths between the Official Visitor Screening Center located on Pennsylvania Avenue and other main building entrances off the courtyard. The “landscaping” was low to no maintenance (artificial turf options were encouraged).

This project was considered extremely time sensitive to the FBI. The Courtyard was required to be fully available for FBI use before the 2015 FBI Family Day scheduled for the 3rd week in June. Meltech completed the project on time for the FBI Family Day.

Quantico Marine Corp Base Child Development Center

admin November 8, 2020 Leave a reply

NAVFAC Quantico Marine Corp Child Development Center HVAC Repairs in Quantico, Virginia

Meltech completed this project for the Naval Facilities Engineering Command Washington for the repairs to the HVAC systems at the Child Development Center at the Quantico Marine Corp Base in Quantico, Virginia.

Quantico Marine Corp Base Building 3228

admin November 8, 2020 Leave a reply

NAVFAC Quantico Marine Corp Base Building 3228 in Quantico, Virginia

General Synopsis

Meltech completed this project for the Naval Facilities Engineering Command Washington for the replacement of the modular office and installation of a new mezzanine at Building 3228 at Quantico Marine Corps Base in Quantico, Virginia. The project was completed in 3 phases: Phase 1: Demolition and Removal; Phase II: Installation; and Phase III: Installation of Storage Racks.

Further Details

Phase I – Demolition and Removal

Demolition and removal of preexisting pre-fabricated office and security cage.   

Phase II – Installation

Installation of a four wall single story, load bearing modular office with above Mezzanine in the Northeast comer of building 3228. The new modular office was installed at least 8″ above existing ground level to avoid possible flooding. The modular office required a 2 hour fire separation.

This modular office spanned from the Northeast side of building 3228 to the Westside. (Approximately 19’0″ x 10’0″ = 190 square feet).  The expansion provided enough space to accommodate two (2) workstations at the north side wall and accommodate five (5) single workstations at the southeast corner wall of the office.

The office included (2) two office solid doors 90 min fire rated with all required hardware on south side wall of office along with the installation of a 15′ x 4′ window.

Three (3) outlets in the north side wall, five (5) outlets in the south wall. Two (2) outlets on the east side wall and two (2) outlets on the west wall.

Stairs with hand rails (outside) west side of the office for accessibility to the above office Mezzanine space. Mezzanine required a rail at least 42″‘ high, with a flip over gate at the south side of the mezzanine for loading.

HVAC unit with minimums of 12,000 (BTU) cooling and 10,500 BTU heating. (Note: HVAC was a component of the Modular Office which required the drain lines installed to provide proper drainage of condensation that may cause any damage to the new structure.

Connect all power requirements from the preexisting power box inside of building 3228 for the new pre-fabricated office.

PHASE Ill – Installation of Storage Racks

Installation of Republic Storage rack system type at the Southeast side of building 3228, at locations E I -E3 and F I – F3. Three (3) upright frame columns 10′ high, same gauge as the existing upright at building 3228, and eight (8) Beams 8′ long and eight (8) wiring mesh shelving similar to the one at the current shelving.

Walter Reed National Military Medical Center Bowling Alley

admin November 8, 2020 Leave a reply

NAVFAC Bethesda Bowling Alley

Meltech completed this important project for the Naval Facilities Engineering Commanf Washington at the Walter Reed National Military Medical Center Bowling Alley. This project was for the backfill, compact and plant sod over a low area by the deck of the bowling alley, Building 56, at the National Support Activity, Bethesda, Maryland.

The work was completed on the east side of the outside deck of the Bowling Alley, Building 56. Meltech filled in the low area, compacted the soil and placed sod over the newly placed soil.

Fort Leonardwood

admin November 8, 2020 Leave a reply

US Army Corps of Engineers Mobile District Fort General Leonard Wood Community Hospital Modular Clinic Site Work in Fort Leonard Wood, MO

This project was result of a MEDCOM CONUS wide contract administered by the U.S. Army Corps of Engineers, Mobile District. Meltech completed this project for the development of a work plan and drawings which detailed all site utilities work, grading and tie-ins.  Modular clinic drawings provided floor plans and utilities layouts, including distribution and load estimates. Work plan also defined all the required outages to electrical and plumbing utilities; and identified all invasive utilities and civil work outside the existing buildings adjacent to the planned clinic. The option that was awarded shortly after was for the complete supply and installation of a new and completely functional Modular Medical Clinic that meet all Local, State, and Federal medical standards and codes.

Fort Detrick and Forest Glen Occupancy Sensors

admin November 8, 2020 Leave a reply

U.S. Army Corps of Engineers Baltimore District Frederick National Laboratory of Cancer Research (FNLCR) Occupancy Sensors, 200 kWPV, and Thermostats at Fort Detrick in Frederick, MD and Forest Glen Annex, Maryland

This project was for the installation of occupancy sensors at the Fort Detrick and Forest Glen Annex for the reduction of energy usage garrison wide through the use of occupancy sensors and modified boiler controls. The projects objectives were to reduce energy usage garrison wide through the use of occupancy sensors and modified boiler controls by providing roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels installed on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material.

The existing roofing system and its attachment to the existing structural roof framing system were evaluated and modified, to support the 200 kW roof mounted PV system. Meltech provided modifications to the existing roof system design and construction for the entire facility roof system, and including all necessary ancillary and incidental work necessary to maintain a watertight roof system installation while allowing for the installation of the 200 kW roof mounted PV system. We coordinated with system manufacturer to maintain existing system warranty. We followed all manufactures written recommendations and recertified the roof following construction.

We provided a roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels were provided on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material. The project consisted of three distinct parts: installation of occupancy sensors in 27 different buildings throughout the base and one at the Forest Glen Annex, installation of a roof mounted solar array on Building 693, and modifications to two boiler control sequences in Building 1532. Various types of occupancy sensors were utilized based on the construction and configurations of the rooms in which the lighting fixtures are going to be controlled. A blend of wall mounted, ceiling mounted, wireless, line voltage, and low voltage sensors were used. The buildings have were surveyed and the most beneficial and cost effective occupancy sensor applications were been identified. Wireless occupancy sensors were designated where wired sensors would result in significant architectural wall repair and disruption during construction. Low voltage sensors with power packs were specified where the coverage of multiple occupancy sensors to control one lighting circuit was required. Line voltage ceiling mounted sensors were provided where exposed conduit and conductors make interception of existing circuits a relatively simple matter. Wall mounted switch type occupancy sensors were provided in private office and other small rooms where existing switches can be replaced in existing outlet boxes to achieve appropriate coverage. Meltech provided modifications to existing area lighting systems consisting of fluorescent, metal halide, and incandescent, lighting to include occupancy sensors for automatic shut-off of fixtures in unoccupied spaces.

The work was completed on the following buildings:

Bldg. 243 – Bacteriology Lab
Bldg. 374 – Greenhouse Facility Lab
Bldg. 810 – Headquarters
Bldg. 1077 – CDMRP Building
Bldg. 1405 – AAFES / Post Exchange (Mini Mall) PX/Military Clothing
Bldg. 1430 – Unaccompanied Enlisted Personnel Housing
Bldg. 1529 – Community Activities Center
Bldg. 1533 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1534 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1535 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1536 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1538 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1540 – Certification Testing Information Assurance Training Center
Bldg. 1541 – Civilian Personnel Advisory Center
Bldg. 1545 – Administrative Offices
Bldg. 1546 – Administrative Offices
Bldg. 1674 – Procurement Division Building

 

 


Fort McNair National Defense University

admin November 8, 2020 Leave a reply

US Army Corps of Engineers National Defense University Fort McNair Marshall Hall South Plaza in Washington, DC

General Synopsis 

Meltech completed this important project for the US Army Corps of Engineers Baltimore District for the National Defense University George Marshall Hall at Fort Lesley J. McNair in Washington, DC. The project included the demolition, construction and landscaping (with environmental aspects) in the South Plaza immediately adjacent to Marshall Hall. 

In length of service as an Army post, Fort McNair ranks third and is the home of the National Defense University (NDU). Marshall hall is part of NDU and operations continued uninterrupted at the building throughout the project.

Meltech’s contract consisted of a two-part base bid. The first part of the base bid was for the demolition of concrete paving, utilities, plants, and all other demolition-related site work as shown on plans and specified. The second part of the base bid consisted of construction of an extended sidewalk and re-planting in the area west of 5th Avenue, and other related construction on the Marshall Hall South Plaza together with surrounding landscaping and storm-water management construction.

Since 90% of the buildings on Fort McNair’s 100 acres are historic buildings (built, reconstructed or remodeled prior to 1908) Meltech’s work was, as with that at Arlington National Cemetery above, subject to extremely vigilant oversight by the U.S. Army Corps of Engineers. For example, backfill materials had to be placed adjacent to all types of structures, and compacted to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, in order to prevent wedging action or eccentric loading upon or against the structure. Compaction had to be finished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Similarly the placement and treatment of bedding, graded stone, various sands and gravels and other fill materials, was strictly controlled and overseen. 

Further Details 

Divisional work associated with the base bid included:

  • Division 2 work consisted of demolition, deconstruction, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work, placement of select fill and topsoil layers for landfill cover systems on geosynthetic materials.
  • Division 3 work consisted of cast-in-place concrete, precast concrete wall panels with normal-weight aggregate Portland cement concrete, conventional reinforcing, and smooth surface or exposed aggregate facing 
  • Division 4 work consisted of reinforced and non-reinforced masonry.
  • Division 7 work consisted of applying sealants for normal building construction.
  • Division 10 work (Specialties) consisted of a pre-manufactured fabric covered steel shelter structure and vertical metal treillage device that allows for plant and vine support. 
  • Division 12 work consisted of miscellaneous site and street furniture and furnishings including shelters, waste and recycle receptacles, ash urns, tables, and chairs. 
  • Division 26 work consisted of general electrical work at the site, installation of photoconductive lighting control devices for use with exterior lighting systems, and installation of exterior lighting systems.
  • Division 31work consisted of earthwork activities, clearing and disposal of trees, stumps, clearing fences, buildings, and other structures and disposal of debris, trash, and materials resulting from clearing operations, clearing and grubbing.
  • Division 32 work consisted of plant material and irrigation during the establishment 
  • Period, concrete sidewalks and curbs and gutters, constructing a concrete block pavement, seeding, exterior planting, storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), and polyethylene (PE) pipe, sub-drainage systems for drainage of water from under the ground.

 

Meltech received an outstanding performance evaluation for the base bid work and as a result two further optional items were exercised. The first option item was for supply and installation of “Bioswale plantings”, procuring and replacing an electrical manhole ring, refinishing some existing structural elements, and addition of a ground neutral line in the panel box feeding the lights and outlets on the site. Bioswales are landscape elements designed to remove silt and pollution from surface runoff water. They consist of a swaled drainage course with gently sloped sides (less than six percent) and filled with vegetation, compost and/or riprap.  The water’s flow path, either a meandering or almost straight, with wide and shallow ditches, maximizes the time water spends in the swale, thus trapping pollutants and silt. Biological factors also contribute to the breakdown of certain pollutants. This work involved a modification to provide and install an extension of the existing irrigation sprinkler system to two new areas adjacent to the South Plaza and Bioswale. 

The second option item involved the supply and installation of exterior furniture at the site. The major scope elements of the options work were:

  1. Field investigation and measurements for the work
  2. Preconstruction/technical/product submittals and shop drawings
  3. Rigging and hoisting for the work
  4. Protection of existing surfaces
  5. Coordination with other trades
  6. Layout for the work
  7. Site demolition as necessary
  8. Third party testing of the work
  9. Provision of full-time on-site superintendent
  10. Daily cleanup of all trash and debris generated by the work
  11. Hauling and removal of all trash and debris
  12. Coordination, inspection and identification of underground utilities
  13. Furnishing and installing all erosion and sediment control systems
  14. Furnishing and installing all tree protection
  15. Furnishing and installing inlet protection
  16. Furnishing and installing a stabilized construction entrance 
  17. Furnishing and installing all concrete sidewalks, seat walls and footers
  18. Furnishing and installing all paver systems
  19. Furnishing and installing striping
  20. Furnishing and installing all plantings including shrubs  and trees
  21. Furnishing and installing all seeding
  22. All rough and fine grading
  23. Furnishing and installing all perforated under-drain piping
  24. Furnishing and installing all rip-rap and miscellaneous stone
  25. Furnishing and installing all mulch
  26. Ancillary support (permits, licenses, Davis-Bacon, certified payrolls, applic. taxes, etc.)