Fort Detrick Area B

admin February 9, 2021 Leave a reply

US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick

Meltech completed this project for the US Army Corps of Engineers Installation of Electrical Distribution Feeder in Area B at Fort Detrick in Frederick, Maryland. This project was for the installation of a new 3 phase, 4-wire, electric utility distribution feeder (NDF) from Sub 6 (Area A) to Pole 1215 (Area B). 

Meltech was responsible for the engineering, furnishing, installation, and testing (EFI&T), and develop an operational scope of effort. The existing 4160v, 3 phase, 4 wire, distribution feeder (EDF) from Sub 6 to Area B was currently being operated slightly above its design limits. A project at Area B in the planning phase will require the back feeding 5 megawatts of power from Area B “back” to Area A (Sub 6). Since a new substation at Area B was not an option at this time, the NDF decided to initially operate at 4160v until a substation can be installed in the future. Knowing this, the NDF had to be designed for 34.5 kilovolt service under this effort. This will allow the Government to easily transition to the higher service voltage later. 

The project required the installation of a temporary access road through wetlands. Meltech provided a temporary wood panel road for access on and off the project site. Prior to the construction of the temporary access road, Meltech craft labor completed the transplanting of approximately 100 small trees to a temporary holding area for the course of the project for re-transplanting upon project completion. Approximately 1830 LF of 14’ wide temporary mat access road was installed on 3 individual attached impacted plates. 

Meltech provided the auger trucks for the drilling of the pole bases, approximately 80 holes for pole installation. An auger truck was used to plant the poles in the pole bases. Class II 40’-50’ treated poles were installed. After all the poles were set, we built and installed all grounds for each pole, per specification. Meltech provided a bucket truck to complete the installation of all hardware and wire. All of the poles were affixed with crossarms and insulators. Each pole differentiated with the fuse cutouts or lighting arrestors depending on requirements specified. Meltech completed the project pulling a total of (4) 3500kv new wire for each pole installation. The wires included 3 hot wires and 1 ground wire. After all wire pulling was completed and tested, Meltech performed the final termination of the wires.   

All work and materials was completed in accordance with (IAW) the latest National Electric Code (NEC), Original equipment Manufacturer (OEM) requirements, applicable Industry standards, and the SOR/SOW.

Walter Reed National Military Medical Center Tranquil Hall

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Building 62 Tranquil Hall Living Suites

The project was for interior construction, interior finishes, plumbing and selective building demolition. The project was to provide replacement ABA/ADA plumbing fixtures in Building 62 Tranquil Hall Movie Room and Gathering Place Austin’s Playroom Lobby & Warrior Café and living suites, bathrooms and at Walter Reed National Military Medical Center in Bethesda, Maryland. The work was performed on the 3rd floor basement, 2nd floor basement, 1st floor basement, and 1st floor levels.

The project required that a barrier-free design be installed in accordance with the requirements of the Federal Accessibility Standards (UFAS) as required by 42 U.S.C. 4151-4157, Architectural Barriers Act (ABA) of 1968, and consistent with 29 U.S.C. 794, Rehabilitation Act of 1973, but also had to meet the requirements of the Americans with Disabilities Act Accessibility Guidelines (ADAAG).

The fixture replacements included:

  • Removal and replacement of 35 shower/tub units
  • Removal and replacement of 153 kitchen sink faucets
  • Removal and replacement of 306 handheld shower heads (including stainless steel hoses)
  • Furnish and install 153 bidet toilet seats and associated plumbing and electrical GFI outlets to existing spare breakers (this will be installed by surface mounting plumbing and electrical inside laundry room)

Walter Reed National Military Medical Center Steam Lines

admin November 8, 2020 Leave a reply

NAVFAC Replace Steam & Condensate Piping at Walter Reed National Military Medical Center in Bethesda, Maryland

General Synopsis

Meltech completed this project for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. This project was for the replacement of the steam and condensate piping to Buildings 11, 13, 14 and 20.

The project consisted of replacing the steam and condensate piping to Buildings 11, 13, 14 & 20 for the Naval Facilities Engineering Command Washington at the Walter Reed National Military Medical Center in Bethesda, Maryland. The project consisted of replacement of direct buried steam and condensate piping between Utility Tunnel # 5 and the Building 14 Mechanical Room along a partially new alignment and the replacement of steam and condensate piping between Building 16 and Buildings 11 and 27 along the existing Loop # 4 alignment through Manhole STML3504 and a new alignment from Manhole STML3504 to Buildings 11 and 27. The work also included the addition of a manhole to serve future Building 13 and building 20 renovations and the replacement of the Building 27 Manhole STML0304. Sequencing was required to cross connect exiting Loop #4 and Loop #7 in the basement of Building 17 prior to the start of demolition to maintain steam to buildings downstream of Manhole STML1304 during construction. The work was directly completed for Buildings 11, 13, 14 & 20 however the work was located between Buildings 14, 16, 17, 27 and 11.

Further Details

The project started with the goetech and retaining wall engineering and MOT, SCE, AGIP, SSF and portable sediment tank installation. Meltech completed the following:

  • Demolition of existing steam lines
  • Supplied, fitted and insulated approximately 340′  of 5″ SCH  40,  543′  of  3″ SCH  40  and  83′  of  2″  SCH40   black  Multi-Therm 500  direct  buried Steam pipe,
  • Supplied, fitted and insulated approximately 340′  of 3″ SCH 10 and 612′ of 3″ SCH   10 stainless Multi-Therm 500  direct  buried  condensate pipe,
  • Supplied, fitted manhole  0904 insulation of new pipe with 2″ insulation and aluminum jacket,
  • Supplied and fitted manhole  3504, new manhold North, new manhole South, Building 14, Building 11, Building 17, Building 27 insulation of new pipe with 2″ insulation  and aluminum jacket,
  • Building   27  interior  connections  to  new  steam   and  condensate lines exclude  any isolating flanges, scales pockets, condensate drain lines, shut off  valves,  check valves,  steam traps, etc. 
  • Provided   sump   pump  unit  for  new  north  and  south manhole and up to 40′ of 2″ piping to closest storm drainage     
  • Access  ladders  for  new  north  manhole,  south manhole and 3504 man holes includes vents and vent caps for new north and south manholes
  • Shop drawing  for buried pipe system (provided  by pipe manufacture)
  • Shop drawings for pipe system located in Mechanical rooms of building 11 and 14 where applicable.
  • Opening up of  valve  in  manhole   1104  after  work  in  building   11  and  17 
  • Replaced Sidewalk and Curb where demoed and Flag Pole Foundation
  • Repaired Spalding Concrete Manhole
  • Reinstallation of the Bike Rack, paving where demo’d, retaining wall across from Bldg. 17 that was demo’d and seeding and mulching of all disturbed areas.

Additional services performed included the geotechnical, concrete thermostat blocks and kickers, provided As-Built Drawings, performed the excavation and removal, welding inspections, imported the backfill materials for utilities, provided landscaping, test pits, sediment and erosion control, installation of temporary construction fence and temporary ADA compliant sidewalks, cathodic protection, sump pump installation and demolition and reinstallation of minor electric.

The main aspects of the work were:

  • Furnishing, installing and insulating approximately 340 feet of 5-inch SCH 40, 543 feet of 3-inch SCH 40, and 83 feet of 2-inch SCH 40 black Multi-Therm 500direct buried steam pipe.
  • Furnishing, installing and insulating approximately 340 feet of 3-inch SCH 10 and 612 feet of 3-inch SCH 10 stainless steel Multi-Therm 500direct buried condensate pipe.
  • Furnishing and installing a number of items, as shown on diagrams, in about one dozen manholes. All new piping to be insulated with 2 inches of insulation and aluminum jacket.
  • Furnishing and installing in Buildings 11, 13, and 14 a number of items as specified in the plans. All new piping to be insulated with 2 inches of insulation and aluminum jacket. Building 11 contained a condensate return unit.
  • Demolition of existing steam and condensate lines.
  • Connections included isolating flanges, scales pockets, condensate drain lines, shut-off valves, check valves, steam traps, etc.
  • Provide sump pumps for identifies units and up to 40 feet of piping to nearest storm drains
  • Provide access ladders, vents and vent caps for identified (on plans) manholes
  • Provide shop drawings for buried pipe system and for pipe systems located in mechanical rooms of Buildings 11 and 14
  • Maintaining strict adherence to, and “paper trail” for compliance with, the American made Act for all steel, pipe, carbon fittings, carbon valves
  • Demolition of asphalt curb and sidewalk covering areas with lines
  • Excavation the areas to install new lines
  • Demolition of old lines
  • Installation of new steam and condensate lines
  • Backfilling of trenches, installation of stone, replacing asphalt, concrete sidewalks and curbs.
  • Supplying Maintenance of Traffic for all operations including road plates
  • Excavation of areas for, and installation of, cathodic protection on newly emplaced lines
  • Final stabilization on excavated area including seed and mulch

Initial activities included:

  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection
  • Geotechnical testing

In addition there was demolition of an existing site retaining wall, and subsequent replacement of the wall (concrete wall, 7 feet high) plus provision of 30 inch wide wooden walkways.

Related work included:

  • Demolition of then-existing site retaining wall across from Building 17 and subsequent re-installation
  • Removal of flag pole with crane and subsequent reinstallation
  • Demolition of flag pole base and replacement with new base
  • Demolition of five existing light poles and associated equipment
  • New foundation and concrete for five existing light pole bases
  • Removal of bike rack, then reinstallation
  • Demolition of asphalt, curb, paving and sidewalk as appropriate with saw cutting included, and subsequent replacement
  • Supplying Maintenance of Traffic for all operations including steel road plates
  • Demolition of five trees and root pruning of two others, plus demolition of a number of bushes
  • Replacement of bushes
  • Protection of trees
  • Seeding and mulching
  • Set up of erosion and sediment controls including super silt fence
  • Set up of temporary construction fence, orange safety fence, and tree-protection fence
  • Provision of portable sediment tank and dumpster
  • At-grade storm drain inlet protection

Walter Reed National Military Medical Center Larsons Gym

admin November 8, 2020 Leave a reply

NAVFAC Walter Reed National Military Medical Center Convert Part of Warehouse Building 226 to Auxillary Gym in Bethesda, Maryland

Meltech completed this important project for the Naval Facilities Engineering Command Washington for the conversion of part of Building 226 warehouse to an auxillary gym. This work was completed at the Walter Reed National Military Medical Center in Bethesda, Maryland.

The work consisted of the construction of interior partition walls approximately 175ft total length approximately 10.5’ high with 2×8 blocking to the north side of the existing center beam. This reduced the 50% footprint. One wall double sided approximately 40 feet in length with unfinished plywood creating a partition wall off the center of the building running east to west. The west wall was approximately 50 feet in length finished one side with unfinished plywood. The north wall approximately 24 feet in length to the light switch by the door with unfinished plywood, and the east wall from the partition wall approximately 21 feet in length to the roolup door. All plywood to be ¾” tongue and groove subfloor grade.

Meltech completed the relocation of the existing condensate drain line from the AC unit approximately 6 inches towards the rear of the building to provide clearance for the wall construction.

Meltech purchased and installed approximately 2,00 sf of interlocking rubber, “Locktuff”, flooring, minimum of ¾’ thick. Flooring was removable. The flooring installed must be able to be removed at a later date.

Fort Detrick and Forest Glen Occupancy Sensors

admin November 8, 2020 Leave a reply

U.S. Army Corps of Engineers Baltimore District Frederick National Laboratory of Cancer Research (FNLCR) Occupancy Sensors, 200 kWPV, and Thermostats at Fort Detrick in Frederick, MD and Forest Glen Annex, Maryland

This project was for the installation of occupancy sensors at the Fort Detrick and Forest Glen Annex for the reduction of energy usage garrison wide through the use of occupancy sensors and modified boiler controls. The projects objectives were to reduce energy usage garrison wide through the use of occupancy sensors and modified boiler controls by providing roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels installed on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material.

The existing roofing system and its attachment to the existing structural roof framing system were evaluated and modified, to support the 200 kW roof mounted PV system. Meltech provided modifications to the existing roof system design and construction for the entire facility roof system, and including all necessary ancillary and incidental work necessary to maintain a watertight roof system installation while allowing for the installation of the 200 kW roof mounted PV system. We coordinated with system manufacturer to maintain existing system warranty. We followed all manufactures written recommendations and recertified the roof following construction.

We provided a roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels were provided on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material. The project consisted of three distinct parts: installation of occupancy sensors in 27 different buildings throughout the base and one at the Forest Glen Annex, installation of a roof mounted solar array on Building 693, and modifications to two boiler control sequences in Building 1532. Various types of occupancy sensors were utilized based on the construction and configurations of the rooms in which the lighting fixtures are going to be controlled. A blend of wall mounted, ceiling mounted, wireless, line voltage, and low voltage sensors were used. The buildings have were surveyed and the most beneficial and cost effective occupancy sensor applications were been identified. Wireless occupancy sensors were designated where wired sensors would result in significant architectural wall repair and disruption during construction. Low voltage sensors with power packs were specified where the coverage of multiple occupancy sensors to control one lighting circuit was required. Line voltage ceiling mounted sensors were provided where exposed conduit and conductors make interception of existing circuits a relatively simple matter. Wall mounted switch type occupancy sensors were provided in private office and other small rooms where existing switches can be replaced in existing outlet boxes to achieve appropriate coverage. Meltech provided modifications to existing area lighting systems consisting of fluorescent, metal halide, and incandescent, lighting to include occupancy sensors for automatic shut-off of fixtures in unoccupied spaces.

The work was completed on the following buildings:

Bldg. 243 – Bacteriology Lab
Bldg. 374 – Greenhouse Facility Lab
Bldg. 810 – Headquarters
Bldg. 1077 – CDMRP Building
Bldg. 1405 – AAFES / Post Exchange (Mini Mall) PX/Military Clothing
Bldg. 1430 – Unaccompanied Enlisted Personnel Housing
Bldg. 1529 – Community Activities Center
Bldg. 1533 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1534 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1535 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1536 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1538 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1540 – Certification Testing Information Assurance Training Center
Bldg. 1541 – Civilian Personnel Advisory Center
Bldg. 1545 – Administrative Offices
Bldg. 1546 – Administrative Offices
Bldg. 1674 – Procurement Division Building

 

 


Fort McNair National Defense University

admin November 8, 2020 Leave a reply

US Army Corps of Engineers National Defense University Fort McNair Marshall Hall South Plaza in Washington, DC

General Synopsis 

Meltech completed this important project for the US Army Corps of Engineers Baltimore District for the National Defense University George Marshall Hall at Fort Lesley J. McNair in Washington, DC. The project included the demolition, construction and landscaping (with environmental aspects) in the South Plaza immediately adjacent to Marshall Hall. 

In length of service as an Army post, Fort McNair ranks third and is the home of the National Defense University (NDU). Marshall hall is part of NDU and operations continued uninterrupted at the building throughout the project.

Meltech’s contract consisted of a two-part base bid. The first part of the base bid was for the demolition of concrete paving, utilities, plants, and all other demolition-related site work as shown on plans and specified. The second part of the base bid consisted of construction of an extended sidewalk and re-planting in the area west of 5th Avenue, and other related construction on the Marshall Hall South Plaza together with surrounding landscaping and storm-water management construction.

Since 90% of the buildings on Fort McNair’s 100 acres are historic buildings (built, reconstructed or remodeled prior to 1908) Meltech’s work was, as with that at Arlington National Cemetery above, subject to extremely vigilant oversight by the U.S. Army Corps of Engineers. For example, backfill materials had to be placed adjacent to all types of structures, and compacted to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, in order to prevent wedging action or eccentric loading upon or against the structure. Compaction had to be finished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Similarly the placement and treatment of bedding, graded stone, various sands and gravels and other fill materials, was strictly controlled and overseen. 

Further Details 

Divisional work associated with the base bid included:

  • Division 2 work consisted of demolition, deconstruction, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work, placement of select fill and topsoil layers for landfill cover systems on geosynthetic materials.
  • Division 3 work consisted of cast-in-place concrete, precast concrete wall panels with normal-weight aggregate Portland cement concrete, conventional reinforcing, and smooth surface or exposed aggregate facing 
  • Division 4 work consisted of reinforced and non-reinforced masonry.
  • Division 7 work consisted of applying sealants for normal building construction.
  • Division 10 work (Specialties) consisted of a pre-manufactured fabric covered steel shelter structure and vertical metal treillage device that allows for plant and vine support. 
  • Division 12 work consisted of miscellaneous site and street furniture and furnishings including shelters, waste and recycle receptacles, ash urns, tables, and chairs. 
  • Division 26 work consisted of general electrical work at the site, installation of photoconductive lighting control devices for use with exterior lighting systems, and installation of exterior lighting systems.
  • Division 31work consisted of earthwork activities, clearing and disposal of trees, stumps, clearing fences, buildings, and other structures and disposal of debris, trash, and materials resulting from clearing operations, clearing and grubbing.
  • Division 32 work consisted of plant material and irrigation during the establishment 
  • Period, concrete sidewalks and curbs and gutters, constructing a concrete block pavement, seeding, exterior planting, storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), and polyethylene (PE) pipe, sub-drainage systems for drainage of water from under the ground.

 

Meltech received an outstanding performance evaluation for the base bid work and as a result two further optional items were exercised. The first option item was for supply and installation of “Bioswale plantings”, procuring and replacing an electrical manhole ring, refinishing some existing structural elements, and addition of a ground neutral line in the panel box feeding the lights and outlets on the site. Bioswales are landscape elements designed to remove silt and pollution from surface runoff water. They consist of a swaled drainage course with gently sloped sides (less than six percent) and filled with vegetation, compost and/or riprap.  The water’s flow path, either a meandering or almost straight, with wide and shallow ditches, maximizes the time water spends in the swale, thus trapping pollutants and silt. Biological factors also contribute to the breakdown of certain pollutants. This work involved a modification to provide and install an extension of the existing irrigation sprinkler system to two new areas adjacent to the South Plaza and Bioswale. 

The second option item involved the supply and installation of exterior furniture at the site. The major scope elements of the options work were:

  1. Field investigation and measurements for the work
  2. Preconstruction/technical/product submittals and shop drawings
  3. Rigging and hoisting for the work
  4. Protection of existing surfaces
  5. Coordination with other trades
  6. Layout for the work
  7. Site demolition as necessary
  8. Third party testing of the work
  9. Provision of full-time on-site superintendent
  10. Daily cleanup of all trash and debris generated by the work
  11. Hauling and removal of all trash and debris
  12. Coordination, inspection and identification of underground utilities
  13. Furnishing and installing all erosion and sediment control systems
  14. Furnishing and installing all tree protection
  15. Furnishing and installing inlet protection
  16. Furnishing and installing a stabilized construction entrance 
  17. Furnishing and installing all concrete sidewalks, seat walls and footers
  18. Furnishing and installing all paver systems
  19. Furnishing and installing striping
  20. Furnishing and installing all plantings including shrubs  and trees
  21. Furnishing and installing all seeding
  22. All rough and fine grading
  23. Furnishing and installing all perforated under-drain piping
  24. Furnishing and installing all rip-rap and miscellaneous stone
  25. Furnishing and installing all mulch
  26. Ancillary support (permits, licenses, Davis-Bacon, certified payrolls, applic. taxes, etc.)

 

Smithsonian Institution Freer Gallery of Art and Arthur M. Sackler Gallery (Freer|Sackler)

admin November 8, 2020 Leave a reply

Smithsonian Institution Renovate Education Offices at the Freer Gallery of Art and Arthur M. Sackler Gallery (Freer|Sackler) in Washington, DC

General Synopsis 

This project was for the renovation of the Education Offices located at the Smithsonian’s Freer Gallery of Art (FGA) and Arthur M. Sackler Gallery (Freer|Sackler) in Washington, DC. 

The work included the demolition and renovation of current Education Offices located on the Second Floor Level below Grade. The demolition work included the removal of walls, doors and frames, carpeting, miscellaneous built-ins and finishes, lighting, mechanical diffuser and some MEP related equipment. The new work included the gypsum board and metal stud partitions, glazed aluminum framing and doors, a translucent feature wall, new carpeting, ceiling and lighting. The sprinkler, fire alarm, speaker and the mechanical systems were modified to work with the current layout. All the main lines and control systems remained. 

This work was completed in a fully occupied building. The affected areas were screened off and all construction activities were staged in a manner to be the least disruptive to the adjacent spaces. All egress paths remained open and in use for the building occupants. 

Further Details 

This project involved the following disciplines: 

Division 2 – Existing Conditions
Division 6 – Woods, Plastics and Composites
Division 7 – Thermal and Moisture Protection
Division 8 – Openings
Division 9 – Finishes
Division 11 – Equipment
Division 21- Fire Suppression
Division 23 – Heating, Ventilating and Air Conditioning
Division 26 – Electrical
Division 28 – Electronic Safety and Security

One project modification was issued for the Sacklers Archives Cold Storage renovation. The work was for the demolition to include the evacuation of the refrigerant from the cold storage equipment and compressors. Complete the disconnections and make safe dehumidifier and fan coil unit and remove equipment from site. Disconnect existing controls and make safe. The new work included the installation of a new rigid supply and return ductwork, 12×12 fire damper with access door, supply and return registers, fire stop penetrations and the insulation on new ductwork.

Smithsonian Institution National Museum of African Art

admin November 8, 2020 Leave a reply

Smithsonian Institution National Museum of African Art (NMAFA) African Cosmos

Meltech completed this project for the new construction of the African Cosmos Exhibit at the Smithsonian Institution’s National Museum of African Art located at 1100 Independence Avenue S.W. Washington, DC. 

The Work in the base contract included:

    • Metal Fabrications
    • Rough Carpentry
    • Gypsum Boards Assemblies
    • Interior Painting
    • Electrical General Requirements
    • Basic Materials and Methods

Smithsonian Institution Hirshhorn Museum and Sculpture Garden

admin November 8, 2020 Leave a reply

Smithsonian Institution Hirshhorn Museum and Sculpture Garden (HMSG) Supersensorial Exhibit

Meltech was awarded this Task Order through our Indefinite Delivery Indefinite Quantity Term Contract for Construction Services required by the Smithsonian Institution Museums and facilities located in the Washington DC Metro Area Mary and Virginia, plus the Smithsonian Museum facilities located in New York, NY Metropolitan area. 

This was a multi-phased project with multiple subcontractors in an occupied historical facility. Work on the project required the installation of critical elements of work which included: exhibit partitions, cutting, patching and matching of existing work, light fixtures and fire alarms. The premises were occupied during the performance of the work.  Meltech scheduled work activities to minimize interruption of occupants and occupied spaces.  

The work in the base contract included:

  • Demolition of 1275 square feet of gwb partitions
  • Construction of approximately 480 square meters (5200 square feet) of new gwb partitions
  • New construction of approximately 600 square feet of suspended gwb ceiling
  • Electrical work to provide power to artworks as shown in drawings
  • Drywall construction and finishing; wall restoration.
  • Suspended gwb ceiling construction
  • Electrical work to provide power to artworks as shown in drawings

National Security Administration Fort Meade

admin November 8, 2020 Leave a reply

National Security Administration (NSA) Renovate Serverland Room 2 at Fort George G. Meade

Meltech completed this important project for the National Security Administration for the renovation of the Serverland Room 2 at Fort George G. Meade in Fort Meade, Maryland. This project was for the National Security Administration Upgrade Infrastructure in Serverland Room 2. The work includes the following and all incidental related work: Convert Machine Room to Lab Room including demolition of select existing systems, retention and reuse of other existing systems, and installation of new architectural, mechanical, and electrical and fire protection systems/equipment. The work was conducted in a single phase. Work in this phase was required to be substantially complete and ready for occupancy within 210 calendar days after No-tice to proceed.

Major products and systems include the following:

  1. Reuse existing architectural components (walls, raised access floor grid, and acoustical tile ceilings.)
  2. Reuse resisting “house” mechanical system (overhead air distribution.)
  3. Modify chilled water distribution.
  4. New chilled water computer room air conditioning (CRAC) units.
  5. Modify existing lighting system,
  6. New power distribution to server racks and cooling equipment.
  7. Modify existing fire suppression/alarm systems.