Fort Detrick and Forest Glen Occupancy Sensors

admin November 8, 2020 Leave a reply

U.S. Army Corps of Engineers Baltimore District Frederick National Laboratory of Cancer Research (FNLCR) Occupancy Sensors, 200 kWPV, and Thermostats at Fort Detrick in Frederick, MD and Forest Glen Annex, Maryland

This project was for the installation of occupancy sensors at the Fort Detrick and Forest Glen Annex for the reduction of energy usage garrison wide through the use of occupancy sensors and modified boiler controls. The projects objectives were to reduce energy usage garrison wide through the use of occupancy sensors and modified boiler controls by providing roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels installed on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material.

The existing roofing system and its attachment to the existing structural roof framing system were evaluated and modified, to support the 200 kW roof mounted PV system. Meltech provided modifications to the existing roof system design and construction for the entire facility roof system, and including all necessary ancillary and incidental work necessary to maintain a watertight roof system installation while allowing for the installation of the 200 kW roof mounted PV system. We coordinated with system manufacturer to maintain existing system warranty. We followed all manufactures written recommendations and recertified the roof following construction.

We provided a roof mounted solar array on Building 693 in an effort to meet Federal renewable energy production goals. Crystalline solar panels were provided on the southwestern facing roof via clamps and supports made for use with standing seam metal roof material. The project consisted of three distinct parts: installation of occupancy sensors in 27 different buildings throughout the base and one at the Forest Glen Annex, installation of a roof mounted solar array on Building 693, and modifications to two boiler control sequences in Building 1532. Various types of occupancy sensors were utilized based on the construction and configurations of the rooms in which the lighting fixtures are going to be controlled. A blend of wall mounted, ceiling mounted, wireless, line voltage, and low voltage sensors were used. The buildings have were surveyed and the most beneficial and cost effective occupancy sensor applications were been identified. Wireless occupancy sensors were designated where wired sensors would result in significant architectural wall repair and disruption during construction. Low voltage sensors with power packs were specified where the coverage of multiple occupancy sensors to control one lighting circuit was required. Line voltage ceiling mounted sensors were provided where exposed conduit and conductors make interception of existing circuits a relatively simple matter. Wall mounted switch type occupancy sensors were provided in private office and other small rooms where existing switches can be replaced in existing outlet boxes to achieve appropriate coverage. Meltech provided modifications to existing area lighting systems consisting of fluorescent, metal halide, and incandescent, lighting to include occupancy sensors for automatic shut-off of fixtures in unoccupied spaces.

The work was completed on the following buildings:

Bldg. 243 – Bacteriology Lab
Bldg. 374 – Greenhouse Facility Lab
Bldg. 810 – Headquarters
Bldg. 1077 – CDMRP Building
Bldg. 1405 – AAFES / Post Exchange (Mini Mall) PX/Military Clothing
Bldg. 1430 – Unaccompanied Enlisted Personnel Housing
Bldg. 1529 – Community Activities Center
Bldg. 1533 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1534 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1535 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1536 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1538 – Unaccompanied Enlisted Personnel Housing Barracks
Bldg. 1540 – Certification Testing Information Assurance Training Center
Bldg. 1541 – Civilian Personnel Advisory Center
Bldg. 1545 – Administrative Offices
Bldg. 1546 – Administrative Offices
Bldg. 1674 – Procurement Division Building

 

 


Fort McNair National Defense University

admin November 8, 2020 Leave a reply

US Army Corps of Engineers National Defense University Fort McNair Marshall Hall South Plaza in Washington, DC

General Synopsis 

Meltech completed this important project for the US Army Corps of Engineers Baltimore District for the National Defense University George Marshall Hall at Fort Lesley J. McNair in Washington, DC. The project included the demolition, construction and landscaping (with environmental aspects) in the South Plaza immediately adjacent to Marshall Hall. 

In length of service as an Army post, Fort McNair ranks third and is the home of the National Defense University (NDU). Marshall hall is part of NDU and operations continued uninterrupted at the building throughout the project.

Meltech’s contract consisted of a two-part base bid. The first part of the base bid was for the demolition of concrete paving, utilities, plants, and all other demolition-related site work as shown on plans and specified. The second part of the base bid consisted of construction of an extended sidewalk and re-planting in the area west of 5th Avenue, and other related construction on the Marshall Hall South Plaza together with surrounding landscaping and storm-water management construction.

Since 90% of the buildings on Fort McNair’s 100 acres are historic buildings (built, reconstructed or remodeled prior to 1908) Meltech’s work was, as with that at Arlington National Cemetery above, subject to extremely vigilant oversight by the U.S. Army Corps of Engineers. For example, backfill materials had to be placed adjacent to all types of structures, and compacted to at least 90 percent laboratory maximum density for cohesive materials or 95 percent laboratory maximum density for cohesionless materials, in order to prevent wedging action or eccentric loading upon or against the structure. Compaction had to be finished by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, vibratory compactors, or other approved equipment. Similarly the placement and treatment of bedding, graded stone, various sands and gravels and other fill materials, was strictly controlled and overseen. 

Further Details 

Divisional work associated with the base bid included:

  • Division 2 work consisted of demolition, deconstruction, dismantling, reconditioning and disposal of existing building materials, equipment and utilities as a part of new construction or renovation work, placement of select fill and topsoil layers for landfill cover systems on geosynthetic materials.
  • Division 3 work consisted of cast-in-place concrete, precast concrete wall panels with normal-weight aggregate Portland cement concrete, conventional reinforcing, and smooth surface or exposed aggregate facing 
  • Division 4 work consisted of reinforced and non-reinforced masonry.
  • Division 7 work consisted of applying sealants for normal building construction.
  • Division 10 work (Specialties) consisted of a pre-manufactured fabric covered steel shelter structure and vertical metal treillage device that allows for plant and vine support. 
  • Division 12 work consisted of miscellaneous site and street furniture and furnishings including shelters, waste and recycle receptacles, ash urns, tables, and chairs. 
  • Division 26 work consisted of general electrical work at the site, installation of photoconductive lighting control devices for use with exterior lighting systems, and installation of exterior lighting systems.
  • Division 31work consisted of earthwork activities, clearing and disposal of trees, stumps, clearing fences, buildings, and other structures and disposal of debris, trash, and materials resulting from clearing operations, clearing and grubbing.
  • Division 32 work consisted of plant material and irrigation during the establishment 
  • Period, concrete sidewalks and curbs and gutters, constructing a concrete block pavement, seeding, exterior planting, storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), and polyethylene (PE) pipe, sub-drainage systems for drainage of water from under the ground.

 

Meltech received an outstanding performance evaluation for the base bid work and as a result two further optional items were exercised. The first option item was for supply and installation of “Bioswale plantings”, procuring and replacing an electrical manhole ring, refinishing some existing structural elements, and addition of a ground neutral line in the panel box feeding the lights and outlets on the site. Bioswales are landscape elements designed to remove silt and pollution from surface runoff water. They consist of a swaled drainage course with gently sloped sides (less than six percent) and filled with vegetation, compost and/or riprap.  The water’s flow path, either a meandering or almost straight, with wide and shallow ditches, maximizes the time water spends in the swale, thus trapping pollutants and silt. Biological factors also contribute to the breakdown of certain pollutants. This work involved a modification to provide and install an extension of the existing irrigation sprinkler system to two new areas adjacent to the South Plaza and Bioswale. 

The second option item involved the supply and installation of exterior furniture at the site. The major scope elements of the options work were:

  1. Field investigation and measurements for the work
  2. Preconstruction/technical/product submittals and shop drawings
  3. Rigging and hoisting for the work
  4. Protection of existing surfaces
  5. Coordination with other trades
  6. Layout for the work
  7. Site demolition as necessary
  8. Third party testing of the work
  9. Provision of full-time on-site superintendent
  10. Daily cleanup of all trash and debris generated by the work
  11. Hauling and removal of all trash and debris
  12. Coordination, inspection and identification of underground utilities
  13. Furnishing and installing all erosion and sediment control systems
  14. Furnishing and installing all tree protection
  15. Furnishing and installing inlet protection
  16. Furnishing and installing a stabilized construction entrance 
  17. Furnishing and installing all concrete sidewalks, seat walls and footers
  18. Furnishing and installing all paver systems
  19. Furnishing and installing striping
  20. Furnishing and installing all plantings including shrubs  and trees
  21. Furnishing and installing all seeding
  22. All rough and fine grading
  23. Furnishing and installing all perforated under-drain piping
  24. Furnishing and installing all rip-rap and miscellaneous stone
  25. Furnishing and installing all mulch
  26. Ancillary support (permits, licenses, Davis-Bacon, certified payrolls, applic. taxes, etc.)

 

Fort Belvoir Design Build HAZMAT Facility

admin November 8, 2020 Leave a reply

US Army Corps Alterations and Repairs to Building 1495 HAZMAT Facility in Fort Belvoir, Virginia

This project was for the design and build-out of historical Building 1495 HAZMAT Facility in Fort Belvoir, Virginia. The work included the removal and replacement of the existing metal sheathing, metal wall panels, the replacement of existing windows and the installation of high efficiency heat pump systems. 

The project Exterior work included the removal of all existing sheathing including louvers on west side of facility; replacement of existing exterior metal wall panels; replacement of existing windows and replacement of one double door on east side with new window. All windows were to be double pane, argon gas filled, with low-e coating. The exterior work also included the replacement of exterior entry doors / frames; replacement of roll up doors / frames; replacement of gutters and downspouts; provided exterior LED facility lighting (wallpacks) with auto sensors and programmable time clocks. 

Site work included the installation of new automatic perimeter entry gate the end of perimeter fence and the installation of a culvert, suitable fill and asphalt to create new entry to facility. 

Interior Demolition consisted of the removal of all existing equipment including oil boiler, air handler, existing duct system, exterior air condition unit, warehouse space heaters and controls and the disconnection of the heating oil tank. The interior demolition work also included the removal of existing drop ceilings, light fixtures, wall finishes, and floor finishes in the administration portion of the facility. 

The HVAC work included the installation of high efficiency heat pump system with associated duct work for administrative area. Meltech provided new unit heaters in warehouse. New system was installed in compliance with NFPA 30 for use in a HAZMAT Facility. Meltech coordinated this work with the Washington Gas Company for the extension of the gas line to the building and any associated work. We air sealed the mechanical room, exhaust duct / fan with duct mastic to eliminate air leakage into the administration area and completed the replacement of two exhaust fans in the warehouse. 

Fire Alarm/Suppression System work included the installation of new addressable fire alarm system and modification to existing water sprinkler system to provide coverage of administrative area. The work also included the installation of new foam based system suitable for hazardous material storage facility for coverage of warehouse portion of facility. 

Electrical work consisted of the assessment of all electrical service panels for capacity to receive new load from HVAC equipment and provide sufficient space capacity. Panel repairs and wiring completed where needed. Work also included the replacement of electrical outlets and switches in warehouse with fixtures compliant with NFPA 70 class 1 Division 2 Material Storage Areas; reconfiguration of electrical outlets and switches according to new floor plans in administrative area; replacement of existing warehouse area fluorescent lights with high efficiency fluorescent fixtures with electronic ballasts and individual motion sensors. Light locations same as existing and the replacement of existing administrative area fluorescent lights with interior LED lights. 

Architectural work consisted of the reconfiguration of interior partitions based on new space plan provided. Final space dimensions were coordinated with end user; exterior wall in administrative space were insulated to the maximum extent possible. Walls furred out where necessary. The work included the replacement of the interior doors/frames; installation of approximately 8 foot base cabinet run in office with sink and laminate countertops. The work also included the replacement of the existing floors with new VCT in the administrative space; painted all administrative area and restroom walls including partition wall with warehouse (both sides) and the replacement of restroom stall partitions and installation of floor ceramic tile. 

Plumbing work included the replacement of all restroom fixtures including toilets, sinks, faucets, urinals and showers and provided the renovation of all restrooms to meet current applicable plumbing and ADA codes. Meltech provided and installed two frost-proof hose bibs to the South and North sides of building and access to the plumbing in bathroom for the potential waste and water connections for sink in the office with sink and laminate countertops. The work was coordinated with end user to for color and material selections. Meltech also provided a single use female restroom with all required plumbing fixtures and accessories. 

Warehouse work included the installation of a perimeter containment system within the warehouse portion of the facility utilizing a 6inch high concrete berm along majority of the facility perimeter, concrete berms in front of the rollup doors, and trench drains in front of access doors; paint the floor coating in entire warehouse area; installation of durable marking tape on the floor to delineate different storage areas of the warehouse; installation of additional eye wash into warehouse area; replacement of rusted sheet metal cladding throughout interior of building. The work included the redesign of the access gate. Meltech provided and installed 80’ of commercial grade steel pallet racks inside the warehouse for equipment and material storage, capable of accepting a 4’x4’ pallet with 55 gallon drum on bottom and top levels. 

The Communications work included the reconfiguration of communication wiring and data and phone terminals to conform to new floor plans. The work required that a minimum of 8 data / phone terminals. Meltech also installed jumper to wall mounted computer display. We designed cable runs and drop locations and installed cable trays. Meltech purchased and installed prefabricated hazardous storage material containers and placed them outside the building while the renovation was ongoing. The hazardous storage material containers were returned inside the building upon completion of the project. 

Polychlorinated Biphenyl (PCB) Cleanup – The Fort Belvoir Directorate of Public Works (DPW) Environmental and Natural Resources (ENRD) are responsible for ensuring compliance with all applicable environmental regulations. Meltech was required to obtain a DPW Excavation Permit (subsurface utility clearance) from the DPW-Construction Management Division prior to all activities requiring any excavation or other subsurface work. A very large portion of this contract was for remedial work for the Polychlorinated Biphenyl (PCB) cleanup. The affected areas of concrete and soil were returned to original condition. Clean soils were placed into the area, and compacted to 95% ASTM D-698 compaction. New asphalt was placed atop the compacted areas and covered completed to allow vehicles to drive over it. It was required to be strong enough for large, heavy, equipment and trucks to safely drive over. 

Sustainable Design Elements 

The contract had several sustainability design requirements to be met. All mechanical, lighting, windows, roofing systems, wall insulations, utility meters, hot water heaters, interior plumbing fixtures, outdoor water, paint adhesives, and sealants and carpet to meet the current Department of Energy Purchasing Specifications for Energy Efficient Products listed on the Federal Energy Management Program, Sheet Metal and Air Conditioning Contractor’s National Association Indoor Air Quality Guidelines for Occupied  Buildings under Construction, 1995, Energy Star or FEJ\1P (Federal Energy Management  Program) ratings, Energy Standard for Buildings except Low-Rise Residential, International Energy Conservation Code, State of Virginia Ia 9 VAC 5-40 Emission Standard for Architectural  and Industrial Maintenance Coating (Rule 4-49) and Carpet and Rug Institute  Green Label program.